Targets for 2005
DowDateDescriptionLocationPerson
Tue Sep 13 Pick up 4 wear plates from Gadston . Anderson
Mon Sep 19 Cycle 7 Request Deadline . Prestage
Tue Sep 20 Take six spider baskets to Maryland for repairs . Anderson
Thu Sep 22 Cycle 7 Planning Meeting Rm. 137 Prestage
Tue Sep 27 NSF Software Review NSF Prestage
Fri Sep 30-Oct 2 Forsyth Astronomical Society 40-Ft. Heatherly
Sat Oct 1 Controlled Deer Hunt GB Site Wirt
Thu Oct 6 Controlled Deer Hunt GB Site Wirt
Fri Oct 7 Controlled Deer Hunt GB Site Wirt
Sat Oct 8 Controlled Deer Hunt GB Site Wirt
Thu Oct 13 Controlled Deer Hunt GB Site Wirt
Fri Oct 14 Controlled Deer Hunt GB Site Wirt
Fri Oct 21- 23 Villanova Astronomical Society, Adric Riedel 40-Ft. Heatherly
Mon Oct 24- 25 Spencer MIddle School, Nancy Moore 40-Ft. Heatherly
Wed Oct 26- 27 Spencer Middle School, Nancy Moore 40-Ft. Heatherly
Fri Nov 4 Cycle 8 Request Deadline . Prestage
Tue Nov 8 Cycle 8 Planning Meeting Rm. 137 Prestage
Fri Nov 11 NRAO Holiday - Veteran's Day . .
Wed Nov 23 GBT Shutdown (7 p.m. to Friday 7 a.m.) (severe network interruption) GBT Anderson
Thu Nov 24 NRAO Holiday - Thanksgiving . .
Fri Nov 25 NRAO Holiday - Day afater Thanksgiving . .
Fri Dec 23 NRAO Holiday - Christmas Eve (observed) . .
Mon Dec 26 NRAO Holiday - Christmas Day (observed) . .
Notes: JL-Jansky Lab, JL Aud - JL Auditorium, NJL-New addition to the Jansky Lab, NCR - New Conference Room, TC - Tour Center, RA - Recreation Area, Sci. Ctr. - Science Center [Meeting regularly scheduled for 11:45 am in Rm. 137]
 
Targets  Open Positions   GBT Receivers   Past Targets  
GB Telescope Operations Home Page   GB Home Page  

Open Positions
Division, PositionLocBudgetReq #PostingStartNameStatus
Assistant Director GB CV CV2319 09/01/05 . . .
Computer, Jr Sys Admin GB GB GB2301 07/11/05 . . .
Electronics Technician (RFI) GB GB GB2293 05/25/05 . . .
() - Target date; Status: A-Awating approval, Pt-Part time, Tr-Transfer, Te-Temporary, F-Temporarily frozen, I-Interviewing
 
Targets  Open Positions   GBT Receivers   Past Targets  
GB Telescope Operations Home Page   GB Home Page  

GBT Receivers
Receiver (GHz)BandLocationPolarization# BeamsTrec(k)Tsys(k)InstalledAvailable
.290 - .395 340 Prime F. Linear/Circular 1 14 70 . .
.385 - .520 450 Prime F. Linear/Circular 1 . 57 . .
.510 - .690 600 Prime F. Linear/Circular 1 . 48 . .
.680 - .920 800 Prime F. Linear/Circular 1 . 24.5 . .
.910 - 1.23 PF2 Prime F. Linear/Circular 1 . 21.9 Storage .
1.15 - 1.73 L Greg. Linear/Circular 1 6 20 . .
1.73 - 2.60 S Greg. Linear/Circular 1 8 - 12 24 . .
3.95 - 5.85 C Greg. Linear/Circular 1 12 25 . .
8.00 - 10.1 X Greg. Circular 1 13 21 - 27 . .
12.00 - 15.4 Ku Greg. Circular 2 14 24 - 30 . .
18.00 - 22.4 K Greg. Circular 2 19 38 . .
22.00 - 26.50 K Greg. Circular 2 23 42 . .
26.00 - 40.00 Ka Greg. Circular 2 20 35 Repair E(10/01/05)
40.00 - 52.00 Q Greg. Circular 2 30 35 - 160 . E(10/01/05)
68.00 - 92.00 W Greg. Linear 2 70 . Dev E(01/01/07)
90.00 - 115.00 W Greg. . . . . Hold .
Holography . Greg . . . . . .
80.0 - 100.0 Penn Bol Greg . . 0.5 mJy/sqrt(t) . Dev .
Notes: Status - Blank => rcvr on GBT and operational; Dev => rcvr in development; Hold => rcvr planned but development not yet started; Repair => rcvr in shop for repairs or modification; Storage => reveiver ready for use but currently in storage Date - A => astronomy available date; E => Engineering available date; N => needed date * => requires at least three weeks to install on telescope from storage .
 