Green Bank Coordination Meeting Summary

for Monday, Feb 3, 2003

Targets  Open Positions   GBT Receivers   Past Targets  
GB Telescope Operations Home Page   GB Home Page  

Targets for 2001
DowDateDescriptionLocationPerson
Mon Oct 8-Jan 31 Construction of NRAO Education and Visitor Center . Wirt
Notes: JL-Jansky Lab, JL Aud - JL Auditorium, NJL-New addition to the Jansky Lab, NCR - New Conference Room, TC - Tour Center, RA - Recreation Area [Meeting regularly scheduled for 1pm in the NCR]
 
Targets for 2002
DowDateDescriptionLocationPerson
Mon Nov 4-Jul 31 Construction of New Dormitory . Wirt
Sun Dec 1-Feb 28 Repair and inst. of RFI window shields in GBT and OVLBI cntrl rms JL Acree
Notes: JL-Jansky Lab, JL Aud - JL Auditorium, NJL-New addition to the Jansky Lab, NCR - New Conference Room, TC - Tour Center, RA - Recreation Area [Meeting regularly scheduled for 1pm in the NCR]
 
Targets for 2003
DowDateDescriptionLocationPerson
Thu Jan 30-Feb 2 Glenville State College, Joe Evans 40 Ft Heatherly
Fri Jan 31 Complete installation of indoor antenna range Anechoic Ch Wirt/Ford
. Jan 31 Complete installation of RFI rack for network switches JL Childers
. Jan 31 Complete site LAN upgrade JL Childers
Mon Feb 3- 28 Paint inside of Residence Hall Apts,Rms and Kitchen RH Wirt
Fri Feb 7 Release Planning complete for M&C 3.12 . Radziwill
Wed Feb 12 Release of M&C 3.11 . Radziwill
Fri Feb 14 Complete installation of QD access ladders GBT Morton
. Feb 14 RFI mitigation of FA servo system complete GBT Weadon
Mon Feb 17 NRAO Holiday - President's Day . .
Fri Mar 7 Release Planning complete for M&C 3.13 . Radziwill
Wed Mar 12 Release of M&C 3.12 . Radziwill
Fri Mar 14- 16 Glenelg High School, Deano Smith 40 Ft Heatherly
Sat Apr 5- 6 GW Community College, Caroline Cox 40 Ft Heatherly
Mon Apr 14- 16 Visiting Committee Meeting JL Aud Jewell
Fri Apr 18 Release Planning complete for M&C 3.14 . Radziwill
. Apr 18 NRAO Holiday . .
Wed Apr 23 Release of M&C 3.13 . Radziwill
Wed Apr 30 Mothball 20m . Chestnut
. Apr 30 Upgrade east feeder switch gear . Wirt
. Apr 30 Complete installation of window upgrades in NRAO houses . Wirt
Thu May 1 Complete installation of sidewalks GBT site Wirt
. May 1- 30 Installation of the Tennis court sealant RA Wirt
Tue May 6- 7 Tygarts Valley High School, D. Rice 40 Ft Heatherly
Mon May 26- 31 Chautauqua JL Aud Heatherly
. May 26 NRAO Holiday - Memorial Day . .
Fri May 30 Release Planning complete for M&C 3.15 . Radziwill
Mon Jun 2- 4 Business Manager Meeting JL Aud Holstine
Wed Jun 4 Release of M&C 3.14 . Radziwill
Thu Jun 12- 14 Gettysburg College, Dick Cooper 40 Ft Heatherly
Sun Jun 15- 21 Hands on Universe JL Aud Heatherly
Mon Jun 23- 24 Harrisonburg Summer Science Experience 40 Ft Heatherly
Thu Jun 26- 27 Mountain Institute Astronomy (camping out) 40 Ft Heatherly
Fri Jun 27 Release Planning complete for M&C 3.16 . Radziwill
Wed Jul 2 Release of M&C 3.15 . Radziwill
Fri Jul 4 NRAO Holiday - Independence Day . .
Sun Jul 13- 20 NASA Goddard / NRAO Joint Workshop JL Aud .
Sun Jul 27- 29 SARA JL Aud Heatherly
Fri Aug 1 Release Planning complete for M&C 3.17 . Radziwill
Wed Aug 6 Release of M&C 3.16 . Radziwill
Sun Aug 10- 17 Single Dish Summer School JL Aud Jewell
Mon Sep 1 NRAO Holiday - Labor Day . .
Fri Sep 12 Release Planning complete for M&C 3.18 . Radziwill
Wed Sep 17 Release of M&C 3.17 . Radziwill
Mon Oct 13 NRAO Holiday - Columbus Day . .
Fri Oct 17 Release Planning complete for M&C 3.19 . Radziwill
Wed Oct 22 Release of M&C 3.18 . Radziwill
Thu Nov 27 NRAO Holiday - Thanksgiving day. . .
Fri Nov 28 NRAO Holiday . .
Wed Dec 10 Release of M&C 3.19 . Radziwill
Wed Dec 24 NRAO Holiday - Christmas Eve . .
Thu Dec 25 NRAO Holiday - Christmas Day . .
Fri Dec 26 NRAO Holiday . .
Notes: JL-Jansky Lab, JL Aud - JL Auditorium, NJL-New addition to the Jansky Lab, NCR - New Conference Room, TC - Tour Center, RA - Recreation Area [Meeting regularly scheduled for 1pm in the NCR]
 
Targets  Open Positions   GBT Receivers   Past Targets  
GB Telescope Operations Home Page   GB Home Page  

Open Positions
Division, PositionLocBudgetReq #PostingStartNameStatus
Basic Research, Jansky Fellow GB CV . . (02/03/03) Y. Kovalev .
Business, Administrative Assistant GB GB GB1105 10/30/02 . . .
Business, Graphics Artist GB GB GB1104 10/30/02 . . .
Electronics, Technician GB GB GB2250 11/04/02 . . .
Electronics, Technician GB GB GB2258 01/15/03 . . .
Fiscal, Accounting Clerk GB GB GB2257 01/03/03 . . .
() - Target date; Status: A-Awating approval, Pt-Part time, Tr-Transfer, Te-Temporary, F-Temporarily frozen
 
Targets  Open Positions   GBT Receivers   Past Targets  
GB Telescope Operations Home Page   GB Home Page  

GBT Receivers
Receiver (GHz)BandLocationPolarization# BeamsTrec(k)Tsys(k)InstalledAvailable
.290 - .395 340 Prime F. Linear/Circular 1 14 70 . .
.385 - .520 450 Prime F. Linear/Circular 1 . 57 . .
.510 - .690 600 Prime F. Linear/Circular 1 . 48 . .
.680 - .920 800 Prime F. Linear/Circular 1 . 24.5 . .
.910 - 1.23 PF2 Prime F. Linear/Circular 1 . 21.9 Dev .
1.15 - 1.73 L Greg. Linear/Circular 1 6 20 . .
1.73 - 2.60 S Greg. Linear/Circular 1 8 - 12 24 . .
3.95 - 5.85 C Greg. Linear/Circular 1 12 25 Repair A - (02/14/03)
8.00 - 10.1 X Greg. Circular 1 13 21 - 27 . .
12.00 - 15.4 Ku Greg. Circular 2 14 24 - 30 Repair A - (02/14/03)
18.00 - 22.4 K Greg. Circular 2 19 38 . .
22.00 - 26.50 K Greg. Circular 2 23 42 . .
26.50 - 40.00 Ka Greg. Circular 2 . . Dev .
40.00 - 50.00 Q Greg. Circular 4 30 35 - 160 Storage * .
68.00 - 92.00 W Greg. Linear 2 70 . Dev .
90.00 - 115.00 W Greg. . . . . Hold .
Holography . Greg . . . . . .
Notes: Status - Blank => rcvr on GBT and operational; Dev => rcvr in development; Hold => rcvr planned but development not yet started; Repair => rcvr in shop for repairs or modification; Storage => reveiver ready for use but currently in storage Date - A => available date; N => needed date * => requires at least three weeks to install on telescope from storage .
 
Targets  Open Positions   GBT Receivers   Past Targets  
GB Telescope Operations Home Page   GB Home Page  

Generated by C.Bignell 01/27/2003