Green Bank Coordination Meeting Summary

for Monday, Jan 13, 2003

Targets  Open Positions   GBT Receivers   Past Targets  
GB Telescope Operations Home Page   GB Home Page  

Targets for 2001
DowDateDescriptionLocationPerson
Mon Oct 8-Jan 31 Construction of NRAO Education and Visitor Center . Wirt
Notes: JL-Jansky Lab, JL Aud - JL Auditorium, NJL-New addition to the Jansky Lab, NCR - New Conference Room, TC - Tour Center, RA - Recreation Area [Meeting regularly scheduled for 1pm in the NCR]
 
Targets for 2002
DowDateDescriptionLocationPerson
Mon Nov 4-Jul 31 Construction of New Dormitory . Wirt
Sun Dec 1-Jan 30 Repair and inst. of RFI window shields in GBT and OVLBI cntrl rms JL Acree
Notes: JL-Jansky Lab, JL Aud - JL Auditorium, NJL-New addition to the Jansky Lab, NCR - New Conference Room, TC - Tour Center, RA - Recreation Area [Meeting regularly scheduled for 1pm in the NCR]
 
Targets for 2003
DowDateDescriptionLocationPerson
Sun Jan 5- 9 AAS Meeting Seattle .
Mon Jan 6- 8 Testing of RFI Room shielding (@100, 300 & 1000 MHz) New Educ Acree
Fri Jan 10 GBT Inspection Plan Complete . Anderson
Mon Jan 13 Repair of RFI Survey antenna GB Site Anderson
Tue Jan 14 Release Planning complete for M&C 3.11 . Radziwill
Wed Jan 15 Complete installation of QD access ladders GBT Morton
. Jan 15- 16 Release of M&C 3.10 . Radziwill
. Jan 15 Installation of indoor antenna range Anechoic Ch Wirt
Fri Jan 31 Complete installation of RFI rack for network switches JL Childers
. Jan 31 Complete site LAN upgrade JL Childers
Tue Feb 11 Release Planning complete for M&C 3.12 . Radziwill
Wed Feb 12 Release of M&C 3.11 . Radziwill
Fri Feb 14 RFI mitigation of FA servo system complete GBT Weadon
Mon Feb 17 NRAO Holiday - President's Day . .
Tue Mar 11 Release Planning complete for M&C 3.13 . Radziwill
Wed Mar 12 Release of M&C 3.12 . Radziwill
Fri Mar 14- 16 Glenelg High School, Deano Smith 40 Ft Heatherly
Fri Apr 18 NRAO Holiday . .
Tue Apr 22 Release Planning complete for M&C 3.14 . Radziwill
Wed Apr 23 Release of M&C 3.13 . Radziwill
Wed Apr 30 Mothball 20m . Chestnut
. Apr 30 Upgrade east feeder switch gear . Wirt
. Apr 30 Complete installation of window upgrades in NRAO houses . Wirt
Thu May 1 Complete installation of sidewalks GBT site Wirt
. May 1- 30 Installation of the Tennis court sealant RA Wirt
Mon May 26- 31 Chautauqua JL Aud Heatherly
. May 26 NRAO Holiday - Memorial Day . .
Tue Jun 3 Release Planning complete for M&C 3.15 . Radziwill
Wed Jun 4 Release of M&C 3.14 . Radziwill
Thu Jun 12- 14 Gettysburg College, Dick Cooper 40 Ft Heatherly
Tue Jul 1 Release Planning complete for M&C 3.16 . Radziwill
Wed Jul 2 Release of M&C 3.15 . Radziwill
Fri Jul 4 NRAO Holiday - Independence Day . .
Sun Jul 13- 20 NASA Goddard / NRAO Joint Workshop JL Aud .
Sun Jul 27- 29 SARA JL Aud Heatherly
Tue Aug 5 Release Planning complete for M&C 3.17 . Radziwill
Wed Aug 6 Release of M&C 3.16 . Radziwill
Mon Sep 1 NRAO Holiday - Labor Day . .
Tue Sep 16 Release Planning complete for M&C 3.18 . Radziwill
Wed Sep 17 Release of M&C 3.17 . Radziwill
Mon Oct 13 NRAO Holiday - Columbus Day . .
Tue Oct 21 Release Planning complete for M&C 3.19 . Radziwill
Wed Oct 22 Release of M&C 3.18 . Radziwill
Thu Nov 27 NRAO Holiday - Thanksgiving day. . .
Fri Nov 28 NRAO Holiday . .
Wed Dec 10 Release of M&C 3.19 . Radziwill
Wed Dec 24 NRAO Holiday - Christmas Eve . .
Thu Dec 25 NRAO Holiday - Christmas Day . .
Fri Dec 26 NRAO Holiday . .
Notes: JL-Jansky Lab, JL Aud - JL Auditorium, NJL-New addition to the Jansky Lab, NCR - New Conference Room, TC - Tour Center, RA - Recreation Area [Meeting regularly scheduled for 1pm in the NCR]
 
Targets  Open Positions   GBT Receivers   Past Targets  
GB Telescope Operations Home Page   GB Home Page  

Open Positions
Division, PositionLocBudgetReq #PostingStartNameStatus
Basic Research, Jansky Fellow GB CV . . (01/13/03) Y. Kovalev .
Business, Administrative Assistant GB GB GB1105 10/30/02 . . .
Business, Graphics Artist GB GB GB1104 10/30/02 . . .
Computer, Software Engineer II GB GB GB2243 05/29/02 (01/20/03) Paul Marganian .
Electronics, Technician GB GB GB2250 11/04/02 . . .
Electronics, Technician GB GB . . . . .
Fiscal, Accounting Clerk GB GB GB2257 01/03/03 . . .
Scientific Services, Asst. Scientist GB GB GB2245 06/19/02 (01/20/03) Karen O'Neil .
() - Target date; Status: A-Awating approval, Pt-Part time, Tr-Transfer, Te-Temporary, F-Temporarily frozen
 
Targets  Open Positions   GBT Receivers   Past Targets  
GB Telescope Operations Home Page   GB Home Page  

GBT Receivers
Receiver (GHz)BandLocationPolarization# BeamsTrec(k)Tsys(k)InstalledAvailable
.290 - .395 340 Prime F. Linear/Circular 1 14 70 . .
.385 - .520 450 Prime F. Linear/Circular 1 . 57 . .
.510 - .690 600 Prime F. Linear/Circular 1 . 48 . .
.680 - .920 800 Prime F. Linear/Circular 1 . 24.5 . .
.910 - 1.23 PF2 Prime F. Linear/Circular 1 . 21.9 Dev .
1.15 - 1.73 L Greg. Linear/Circular 1 6 20 . .
1.73 - 2.60 S Greg. Linear/Circular 1 8 - 12 24 . .
3.95 - 5.85 C Greg. Linear/Circular 1 12 25 . .
8.00 - 10.1 X Greg. Circular 1 13 21 - 27 . .
12.00 - 15.4 Ku Greg. Circular 2 14 24 - 30 . .
18.00 - 22.4 K Greg. Circular 2 19 38 . .
22.00 - 26.50 K Greg. Circular 2 23 42 . .
26.50 - 40.00 Ka Greg. Circular 2 . . Dev .
40.00 - 50.00 Q Greg. Circular 4 30 35 - 160 Storage * .
68.00 - 92.00 W Greg. Linear 2 70 . Dev .
90.00 - 115.00 W Greg. . . . . Hold .
Holography . Greg . . . . . .
Notes: Status - Blank => rcvr on GBT and operational; Dev => rcvr in development; Hold => rcvr planned but development not yet started; Repair => rcvr in shop for repairs or modification; Storage => reveiver ready for use but currently in storage Date - A => available date; N => needed date * => requires at least three weeks to install on telescope from storage .
 
Targets  Open Positions   GBT Receivers   Past Targets  
GB Telescope Operations Home Page   GB Home Page  

Generated by C.Bignell 01/06/2003