Green Bank Coordination Meeting Summary

for Monday, Nov 4, 2002

Targets  Open Positions   GBT Receivers   Past Targets  
GB Telescope Operations Home Page   GB Home Page  

Targets for 2001
DowDateDescriptionLocationPerson
Mon Oct 8-Dec 8 Construction of NRAO Education and Visitor Center . Wirt
Notes: JL-Jansky Lab, JL Aud - JL Auditorium, NJL-New addition to the Jansky Lab, NCR - New Conference Room, TC - Tour Center, RA - Recreation Area [Meeting regularly scheduled for 1pm in the NCR]
 
Targets for 2002
DowDateDescriptionLocationPerson
Wed Jun 19-Oct 31 Construction of Cable building expansion . Wirt
Tue Oct 1- 31 Installation of the Tennis court sealant RA Wirt
Sat Oct 5-Nov 30 Rewiring of power distribution (east feeder) complete . Wirt
Thu Oct 31-Nov 1 GBT Az Track review Meeting JL Aud Jewell
Mon Nov 4-Jun 30 Construction of New Dormitory . Wirt
Thu Nov 7 WVMR Radio program taping (for 2nd Saturday at 10am) - P. Jewell WVMR Station Lockman
Fri Nov 8 Installation of QD access ladders GBT Morton
Fri Nov 15 GBT Inspection Plan Complete . Anderson
Thu Nov 28 NRAO Holiday - Thanksgiving Day . .
Fri Nov 29 NRAO Holiday . .
Sat Nov 30 Complete installation of sidewalks GBT site Wirt
Sun Dec 1-Jan 30 Repair and installation of RFI window shields in GBT and OVLBI cntrl rms JL Acree
Tue Dec 10 GBT Scheduling Committee Meeting NCR Bignell
Tue Dec 24 NRAO Holiday . .
Wed Dec 25 NRAO Holiday - Christmas Day . .
Notes: JL-Jansky Lab, JL Aud - JL Auditorium, NJL-New addition to the Jansky Lab, NCR - New Conference Room, TC - Tour Center, RA - Recreation Area [Meeting regularly scheduled for 1pm in the NCR]
 
Targets for 2003
DowDateDescriptionLocationPerson
Fri Mar 14- 16 Deano Smith 40 Ft Heatherly
Wed Apr 30 Mothball 20m . Chestnut
Mon May 19- 24 Chautauqua JL Aud Heatherly
Thu Jun 12- 14 Gettysburg College 40 Ft Heatherly
Sun Jul 13- 20 NASA / NRAO Joint Workshop JL Aud .
Notes: JL-Jansky Lab, JL Aud - JL Auditorium, NJL-New addition to the Jansky Lab, NCR - New Conference Room, TC - Tour Center, RA - Recreation Area [Meeting regularly scheduled for 1pm in the NCR]
 
Targets  Open Positions   GBT Receivers   Past Targets  
GB Telescope Operations Home Page   GB Home Page  

Open Positions
Division, PositionLocBudgetReq #PostingStartNameStatus
Computer, Software Engineer II GB GB GB2243 05/29/02 (01/20/03) Paul Marganian .
Scientific Services, Asst. Scientist GB GB GB2245 06/19/02 (01/20/03) Karen O'Neil .
() - Target date; Status: A-Awating approval, Pt-Part time, Tr-Transfer, Te-Temporary, F-Temporarily frozen
 
Targets  Open Positions   GBT Receivers   Past Targets  
GB Telescope Operations Home Page   GB Home Page  

GBT Receivers
Receiver (GHz)BandLocationPolarization# BeamsTrec(k)Tsys(k)InstalledAvailable
.290 - .395 340 Prime F. Linear/Circular 1 14 70 . .
.385 - .520 450 Prime F. Linear/Circular 1 . 57 . .
.510 - .690 600 Prime F. Linear/Circular 1 . 48 . .
.680 - .920 800 Prime F. Linear/Circular 1 . 24.5 . .
.910 - 1.23 PF2 Prime F. Linear/Circular 1 . 21.9 Dev A-(02/01/03)
1.15 - 1.73 L Greg. Linear/Circular 1 6 20 . .
1.73 - 2.60 S Greg. Linear/Circular 1 8 - 12 24 . .
3.95 - 5.85 C Greg. Linear/Circular 1 12 25 . .
8.00 - 10.1 X Greg. Circular 1 13 21 - 27 . .
12.00 - 15.4 Ku Greg. Circular 2 14 24 - 30 . .
18.00 - 22.4 K Greg. Circular 2 19 38 Repair A-(11/08/02)
22.00 - 26.50 K Greg. Circular 2 23 42 Repair A-(11/08/02)
26.50 - 40.00 Ka Greg. Circular 2 . . Dev .
40.00 - 50.00 Q Greg. Circular 4 30 35 - 160 Storage * .
68.00 - 92.00 W Greg. Linear 2 70 . Dev .
90.00 - 115.00 W Greg. . . . . Hold .
Holography . Greg . . . . . .
Notes: Status - Blank => rcvr on GBT and operational; Dev => rcvr in development; Hold => rcvr planned but development not yet started; Repair => rcvr in shop for repairs or modification; Storage => reveiver ready for use but currently in storage Date - A => available date; N => needed date * => requires at least three weeks to install on telescope from storage .
 