Green Bank Coordination Meeting Summary

for Tuesday, Sep 4, 2001

Targets  Open Positions   GBT Receivers   Past Targets   GB Home Page  

Targets for 2001
DowDateDescriptionLocationPerson
Mon Jan 22-Aug 30 Terminate new fiber in lab JL Ford
Wed Aug 29- 30 Mainsaver Training (general and supervisor) JL Aud Lawrence
Fri Aug 31 GB deadline for NRAO Newsletter articles . Langston
. Aug 31-Sep 3 Oil Region Astronomical Society - Tim Spuck 40 Ft Heatherly
Sat Sep 1 Issue contract for new education center (awaiting NSF approval) . Holstine
Mon Sep 3 NRAO Holiday - Labor Day . .
Thu Sep 6 WVMR radio program taping (at 2pm - broadcast 2nd Sat) - J. Lockman . Lockman
Fri Sep 7 Installation of Optical Guide Scope complete GBT Prestage
Wed Sep 12 GB Middle School training, RESA IV JL Aud Heatherly
Thu Sep 13- 14 EPO Roundtable JL Aud Lockman
Fri Sep 14 Install drainage system for Laser Monument ZY105 GBT site Wirt
. Sep 14 Installation of A/C in the Machine Shop . Wirt
. Sep 14 Last day to submit requisitions . Holstine
Sat Sep 15 Start construction of NRAO Education and Visitor Center . Wirt
. Sep 15 Install conduit to weather tower GBT site Wirt
Wed Sep 19 PCHS training, RESA IV JL Aud Heatherly
Fri Sep 21 Install warehouse bathroom and septic system GBT site Holstine
. Sep 21 Expansion of Computer Server Room JL Beverage
. Sep 21 Colloquia, "Chandra Imaging of Cluster Cores", B. McNamara, 11:00am JL Aud Minter
Sun Sep 30 Electronic Time Entry test using ADP eTime software complete GB Gibb
. Sep 30 Quadrant detector installation complete GBT Prestage
. Sep 30 Use of Mainsaver within Operations group . Lawrence
. Sep 30 Second of the new cryo compressors fabricated. . Prestage
. Sep 30 Last Day of NRAO Fiscal Year . Holstine
Mon Oct 1 Installation of hoist pad, access pad and sidewalks GBT site Holstine
. Oct 1 Machine Shop Renovations . Holstine
. Oct 1-Jan 30 Construction of NRAO Townhouses . Holstine
. Oct 1 Installation of water and septic to GBT warehouse . Wirt
Thu Oct 4 WVMR radio program taping (at 2pm - broadcast 2nd Sat) - P. Jewell . Lockman
Sat Oct 6- 8 Penn State Erie, Darren Williams 40 Ft Heatherly
Mon Oct 8 NRAO Holiday - Columbus Day . .
Thu Oct 11- 14 Forsyth Astronomical Society, Terry Shore 40 Ft Heatherly
Sun Oct 21- 24 Real Time Programmer's Conference JL Aud Prestage
Fri Oct 26- 28 Villanova University 40 Ft Heatherly
. Oct 26 Jansky Lecture JL Aud .
Tue Oct 30 Detailed Requirements for Observing Asistant III program . Lawrence
Thu Nov 1 Mothball 20m . Chestnut
. Nov 1 MCB monitoring of backup pwr gen. and pwr xfmr complete. GBT Prestage
. Nov 1 New main breaker for power distribution installed . Holstine
. Nov 1 WVMR radio program taping (at 2pm - broadcast 2nd Sat) - G. Langston . Lockman
Wed Nov 7 Rewire site switch . Holstine
. Nov 7 Rewiring of power distribution complete . Holstine
Thu Nov 15 Begin documentation of R&R maintenance procedures using new system . Meadows
. Nov 15 RESA IV Science Bowl JL Aud Heatherly
Thu Nov 22 NRAO Holiday - Thanksgiving Day . .
Fri Nov 23 NRAO Holiday . .
Fri Nov 30 Repair and installation of track covers complete GBT Prestage
Sat Dec 1 Complete design of new dormitory . Holstine
Thu Dec 6 WVMR radio program taping (at 2pm - broadcast 2nd Sat) - D. Balsar . Lockman
Mon Dec 24 NRAO Holiday . .
Tue Dec 25 NRAO Holiday - Christmas Day . .
Mon Dec 31 NRAO Holiday . .
Notes: JL-Jansky Lab, JL Aud - JL Auditorium, NJL-New addition to the Jansky Lab, NCR - New Conference Room, TC - Tour Center, RA - Recreation Area ***** NOTE HOLIDAY ***** Next meeting on Tuesday Sep 4
 
Targets for 2002
DowDateDescriptionLocationPerson
Thu Jan 3 WVMR radio program taping (at 2pm - broadcast 2nd Sat) - F. Ghigo . Lockman
Thu Feb 7 WVMR radio program taping (at 2pm - broadcast 2nd Sat) - J. Braatz . Lockman
Thu Mar 7 WVMR radio program taping (at 2pm - broadcast 2nd Sat) - R. Maddelena . Lockman
Sun May 19- 25 Chautauqua Course JL Aud Heatherly
Mon Jun 10- 15 IUCAF Spectrum Management Meeting JL Aud .
Sun Jun 16- 29 RARECATS JL Aud Heatherly
Sun Jul 14- 20 HOU I JL Aud Heatherly
Sun Jul 28-Aug 3 HOU II JL Aud Heatherly
Fri Aug 2 Construction of NRAO Education and Visitor Center complete . Holstine
Notes: JL-Jansky Lab, JL Aud - JL Auditorium, NJL-New addition to the Jansky Lab, NCR - New Conference Room, TC - Tour Center, RA - Recreation Area ***** NOTE HOLIDAY ***** Next meeting on Tuesday Sep 4
 
Targets  Open Positions   GBT Receivers   Past Targets   GB Home Page  

Open Positions
Division, PositionLocBudgetReq #PostingStartNameStatus
Computer, Assistant Scientist GB GB GB2191 03/08/01 . . .
Computer, Division Head GB GB GB2196 03/19/01 . . .
Computer, Sr. Systems Analyst GB GB GB2219 . (09/01/01) W. Baudler .
Computer, Systems Analyst GB GB GB2192 04/02/01 . . .
Electronics, Digital Eng. GB GB GB2221 . . . .
Electronics, Interference Engineer GB GB GB2184 03/27/01 . . .
Mechanical Eng., Machinist GB GB GB2224 07/25/01 . . .
Scientific Services, 3mm Pgm Scientist GB GB CV2153 . . . .
Telescope Operations, Tel. Operator GB OVLBI GB2226 07/20/01 (09/04/01) E. Jett Pt Te
() - Target date; Status: A-Awating approval, Pt-Part time, Tr-Transfer, Te-Temporary, F-Temporarily frozen
 
Targets  Open Positions   GBT Receivers   Past Targets   GB Home Page  

GBT Receivers
Receiver (GHz)BandLocationPolarization# BeamsTrec(k)Tsys(k)InstalledAvailable
.290 - .395 1-1* Prime F. Linear/Circular 1 14 70 12/01/00 (03/30/01)
.385 - .520 1-2 * Prime F. Linear/Circular 1 . 57 12/01/00 (03/30/01)
.510 - .690 1-3 * Prime F. Linear/Circular 1 . 48 12/01/00 (03/30/01)
.680 - .920 1-4 * Prime F. Linear/Circular 1 . 24.5 12/01/00 (03/30/01)
.910 - 1.23 2 Prime F. Linear/Circular 1 . 21.9 (09/01/01) 2001 +
1.15 - 1.73 L Greg. Linear/Circular 1 6 20 10/20/00 (03/30/01)
1.73 - 2.60 S Greg. Linear/Circular 1 8 - 12 24 10/20/00 (03/30/01)
3.95 - 5.85 C Greg. Linear/Circular 1 12 25 10/20/00 (03/30/01)
8.00 - 10.1 X Greg. Circular 1 13 21 - 27 10/20/00 (03/30/01)
12.00 Ku Greg. Circular 2 14 24 - 30 10/20/00 (03/30/01)
18.00 - 22.4 K Greg. Circular 2 19 38 11/16/00 (03/30/01)
22.00 - 26.50 K Greg. Circular 2 23 42 11/16/00 (03/30/01)
26.50 - 40.00 Ka Greg. ? ? 25 . On Hold .
40.00 - 50.00 Q Greg. Circular 4 30 35 - 160 (09/30/01) (11/01/01)
68.00 - 95.00 W Greg. . . . . On Hold .
90.00 - 115.00 W Greg. . . . . On Hold .
Notes: () - target date; * - share same dewar; + - dates dependent on GBT contractor ? - undecided: multibeams are dual polarized .
 