Targets for 2001
DowDateDescriptionLocationPerson
Mon Jan 22-Jun 30 Terminate new fiber in lab JL Ford
Tue May 1-Jun 30 Set GBT Panel corners to best surface (bird bath to accommodate painting) GBT Prestage
Fri Jun 8 Installation of Feed Arm Laser (right lower unit) GBT Prestage
Sat Jun 9- 15 Hands-on Universe Workshop JL Aud Heatherly
Sun Jun 10- 15 NAIC-NRAO School on Single-Dish Radio Astronomy Arecibo Jewell
Mon Jun 11 GB Rec Pool opens (includes heaters) . Holstine
Fri Jun 15 Specific Plan for Oper. training in General Astron. & Radio Astronomy . Lawrence
. Jun 15 Ship Richmond Receiver to USNO . Chestnut
Sun Jun 17- 30 RARECATS JL Aud Heatherly
Fri Jun 29 Install GBT Feed Arm Lasers (middle units) GBT Prestage
. Jun 29 MCB monitoring of backup pwr gen. and pwr xfmr complete. GBT Prestage
. Jun 29 Installation of telephone to PF & subr. areas complete GBT Prestage
Sun Jul 1 Conversion of Ops Manual using new templates . Lawrence
Mon Jul 2 Contract awarded for Construction of NRAO Education and Visitor Center . Holstine
. Jul 2 Use of Mainsaver within Operations group . Lawrence
Wed Jul 4 NRAO Holiday - Independence Day . .
Thu Jul 5 WVMR Recording of NRAO Radio Show (tba 2nd Sat of month) - Braatz . Lockman
Sun Jul 15- 18 SARA JL Aud Heatherly
. Jul 15 Installation of Optical Guide Scope complete GBT Prestage
Mon Jul 16 Restart of GBT commissioning GBT Prestage
Sat Jul 21- 27 Hand-on Universe Workshop JL Aud Heatherly
Wed Jul 25- 27 NRAO Business Managers Meeting CV Holstine
Sat Jul 28 GB Annual Picnic Rec Area .
. Jul 28 NRAO GB Summer Picnic Rec Area .
Sun Jul 29-Aug 11 RARECATS JL Aud Heatherly
Mon Jul 30 Repair and installation of track covers complete GBT Prestage
. Jul 30 Second of the new cryo compressors fabricated. . Prestage
. Jul 30 Detailed Requirements for Observing Asistant III program . Lawrence
Tue Jul 31 Test of GBT VLBI equipment (using the VLBA) GBT Ghigo
. Jul 31 Electronic Time Entry test using ADP eTime software complete GB Gibb
Wed Aug 1 Start construction of NRAO Education and Visitor Center . Holstine
. Aug 1 New main breaker for power distribution installed . Holstine
. Aug 1 Rewire site switch . Holstine
. Aug 1 Rewiring of power distribution complete . Holstine
. Aug 1 Begin Operations of GBT from the Janksy Lab . Prestage
Sun Aug 12- 19 ERIRA, Penn State, Dan Reichart 40 Ft Heatherly
Mon Aug 13 Begin Astronomical Observations GBT Prestage
Wed Aug 29- 30 Mainsaver Training (general and supervisor) JL Aud Lawrence
Thu Aug 30 Installation of the Feed Arm Lasers (upper units) GBT Prestage
. Aug 30 Quadrant detector installation complete GBT Prestage
Fri Aug 31 GB deadline for NRAO Newsletter articles . Langston
Sat Sep 1 Mothball 20m . Chestnut
. Sep 1 Begin Weekend operations on the GBT GBT Prestage
Mon Sep 3 NRAO Holiday - Labor Day . .
Sat Sep 15 Begin documentation of R&R maintenance procedures using new system . Meadows
Sat Oct 6- 8 Penn State Erie, Darren Williams 40 Ft Heatherly
Mon Oct 8 NRAO Holiday - Columbus Day . .
Thu Nov 22 NRAO Holiday - Thanksgiving Day . .
Fri Nov 23 NRAO Holiday . .
Mon Dec 24 NRAO Holiday . .
Tue Dec 25 NRAO Holiday - Christmas Day . .
Mon Dec 31 NRAO Holiday . .
Notes: JL-Jansky Lab, NJL-New addition to the Jansky Lab, NCR - New Conference Room, TC - Tour Center, RA - Recreation Area
 
Targets for 2002
DowDateDescriptionLocationPerson
Fri Aug 2 Construction of NRAO Education and Visitor Center complete . Holstine
Notes: JL-Jansky Lab, NJL-New addition to the Jansky Lab, NCR - New Conference Room, TC - Tour Center, RA - Recreation Area
 
Targets  Open Positions   GBT Receivers   Past Targets   GB Home Page  

Open Positions
Division, PositionLocBudgetReq #PostingStartNameStatus
Fiscal, Accounting Clerk GB CV GB2203 05/08/01 (06/25/01) G. Pullian .
Computer, Assistant Scientist GB GB GB2191 03/08/01 . . .
Computer, Division Head GB GB GB2196 03/19/01 . . .
Computer, Systems Analyst GB GB GB2192 04/02/01 . . .
Electronics, Digital Engineer GB GB GB2199 04/19/01 (07/01/01) R. McCullough .
Electronics, Digital Technician GB GB GB2187 03/08/01 . . .
Electronics, Interference Engineer GB GB GB2184 03/27/01 . . .
Mechanical Engineering, Designer GB GB GB2189 03/14/01 06/11/01 J. Cromer .
Plant Maintenance, Electrician GB GB GB2175 10/30/00 (07/01/01) B. Goldizen .
Plant Maintenance, Engineer GB GB GB2111 02/15/01 (06/18/01) D. Wirt .
Plant Maintenance, HVAC Plumb. Mech. GB GB GB2193 04/04/01 . . .
Plant Maintenance, Painter GB GB GB2194 04/04/01 . . .
Plant Maintenance, Utility Worker GB GB GB2206 05/28/01 . . .
Scientific Services, 3mm Pgm Scientist GB GB CV2153 . . . .
Scientific Services, Deputy Assist. Dir. GB GB GB2181 01/12/01 06/11/01 R. Prestage .
Telescope Operations, GBT Operator GB GB GB2201 05/01/01 . . .
Telescope Operations, Tele. Mech. GB GB GB2183 03/19/01 . . .
() - Target date; Status: A-Awating approval, Pt-Part time, Tr-Transfer, Te-Temporary, F-Temporarily frozen
 
Targets  Open Positions   GBT Receivers   Past Targets   GB Home Page  

GBT Receivers
Receiver (GHz)BandLocationPolarization# BeamsTrec(k)Tsys(k)InstalledAvailable
.290 - .395 1-1* Prime F. Linear/Circular 1 14 70 12/01/00 (03/30/01)
.385 - .520 1-2 * Prime F. Linear/Circular 1 . 57 12/01/00 (03/30/01)
.510 - .690 1-3 * Prime F. Linear/Circular 1 . 48 12/01/00 (03/30/01)
.680 - .920 1-4 * Prime F. Linear/Circular 1 . 24.5 12/01/00 (03/30/01)
.910 - 1.23 2 Prime F. Linear/Circular 1 . 21.9 (09/01/01) 2001 +
1.15 - 1.73 L Greg. Linear/Circular 1 6 20 10/20/00 (03/30/01)
1.73 - 2.60 S Greg. Linear/Circular 1 8 - 12 24 10/20/00 (03/30/01)
3.95 - 5.85 C Greg. Linear/Circular 1 12 25 10/20/00 (03/30/01)
8.00 - 10.1 X Greg. Circular 1 13 21 - 27 10/20/00 (03/30/01)
12.00 Ku Greg. Circular 2 14 24 - 30 10/20/00 (03/30/01)
18.00 - 22.4 K Greg. Circular 2 19 38 11/16/00 (03/30/01)
22.00 - 26.50 K Greg. Circular 2 23 42 11/16/00 (03/30/01)
26.50 - 40.00 Ka Greg. ? ? 25 . On Hold .
40.00 - 50.00 Q Greg. Circular 4 30 35 - 160 (09/30/01) (11/01/01)
68.00 - 95.00 W Greg. . . . . On Hold .
90.00 - 115.00 W Greg. . . . . On Hold .
Notes: () - target date; * - share same dewar; + - dates dependent on GBT contractor ? - undecided: multibeams are dual polarized .
 
Targets  Open Positions   GBT Receivers   Past Targets   GB Home Page

Generated by C.Bignell 06/11/2001