GBT Commisioning


Project Start Date: Tue 1/2/01
Project Finish Date: Sun 5/5/02

Who Does What

Resources and AssignmentsPercent_Work_CompleteStartFinishWork
Unassigned
0%Tue 1/2/01Mon 4/29/020 days
Electronics ready for continuum commissioning
0%Tue 1/23/01Tue 1/23/010 days
Electronics ready for spectral-line Commissioning
0%Fri 5/4/01Fri 5/4/010 days
Spectrometer ready for general use
0%Fri 8/10/01Mon 8/13/010 days
Electronics Ready for Doppler commissioning
0%Fri 5/4/01Fri 5/4/010 days
Complete 40-52 GHz hardware
0%Tue 1/2/01Tue 1/2/010 days
40-52 GHz Rcvr. ready for use
0%Tue 4/10/01Tue 4/10/010 days
Spectral Processor ready for use
0%Tue 6/26/01Tue 6/26/010 days
Prime Focus 2 Rcvr. ready for use
0%Tue 6/26/01Tue 6/26/010 days
All hardware has been Implemented
0%Mon 4/29/02Mon 4/29/020 days
GBT Observe Ready for stage 1 continuum commissioning
0%Thu 2/15/01Thu 2/15/010 days
GBT Observe Ready for line commissioning
0%Mon 4/30/01Mon 4/30/010 days
GBT Observe ready for Doppler experiments
0%Thu 5/31/01Thu 5/31/010 days
GBT Observe ready for Holography
0%Mon 2/26/01Mon 2/26/010 days
GBT Observe ready for general use
0%Mon 9/24/01Mon 9/24/010 days
Aips++ Ready for Stage 2 Cont. Commissioning
0%Wed 1/10/01Wed 1/10/010 days
Aips++ Ready for Final Cont. Commissioning
0%Fri 1/19/01Fri 1/19/010 days
Aips++ Ready for Holography Commissioning
0%Wed 4/4/01Wed 4/4/010 days
Aips++ Ready for Line Commissioning
0%Tue 5/8/01Tue 5/8/010 days
Aips++ Ready for General Use
0%Tue 9/25/01Tue 9/25/010 days
PF Focus track ready
0%Mon 7/9/01Mon 7/9/010 days
Preliminary Greg. Focus tracking ready
100%Fri 8/3/01Fri 8/3/010 days
High Frequency Greg. focus tracking ready
0%Thu 11/1/01Thu 11/1/010 days
Optical Pointing Complete
0%Tue 7/3/01Tue 7/3/010 days
PF Pointing complete
0%Fri 8/17/01Fri 8/17/010 days
Preliminary Gregorian pointing complete
100%Wed 9/5/01Wed 9/5/010 days
Gregorian high frequency pointing complete
0%Fri 11/23/01Fri 11/23/010 days
1st surface setting
0%Fri 9/21/01Fri 9/21/010 days
2nd surface setting
0%Wed 10/24/01Wed 10/24/010 days
Final Surface setting
0%Tue 10/23/01Tue 10/23/010 days
PF 800 MHz ready for experiments
0%Mon 1/14/02Mon 1/14/020 days
1-2 GHz ready for experiments
0%Thu 1/17/02Thu 1/17/020 days
12-18 GHz ready for experiments
0%Thu 1/24/02Thu 1/24/020 days
40-52 GHz ready for experiments
0%Mon 2/11/02Mon 2/11/020 days
PF 300 MHz ready for experiments
0%Thu 2/28/02Thu 2/28/020 days
2-3 GHz ready for experiments
0%Fri 3/15/02Fri 3/15/020 days
4-6 GHz ready for experiments
0%Tue 3/19/02Tue 3/19/020 days
8-10 GHz Ready for Experiments
0%Wed 3/27/02Wed 3/27/020 days
18-26 GHz ready for experiments
0%Wed 4/10/02Wed 4/10/020 days
PF2 ready for experiments
0%Wed 4/17/02Wed 4/17/020 days
Aips++ Ready for Stage 1 Cont. Commissioning
0%Tue 1/2/01Tue 1/2/010 days
Preliminary VLBI hardware ready
0%Mon 6/4/01Mon 6/4/010 days
VLB/S2 hardware ready for general users.
0%Mon 4/29/02Mon 4/29/020 days
GBT Observe Ready for stage 2 continuum commissioning
0%Fri 6/29/01Fri 6/29/010 days
Optical pointing telescope ready for commissioning
0%Wed 1/31/01Wed 1/31/010 days
Holography hardware ready for commissioning
0%Thu 2/8/01Thu 2/8/010 days
All receivers have been commissioned
0%Wed 4/17/02Wed 4/17/020 days
Measure plate scale
80%Mon 2/26/01Mon 7/9/010 days
Commissioners
20%Tue 1/2/01Fri 5/3/02508 days
DCR tests
100%Wed 1/10/01Thu 1/11/011 day
Test Switch Sig Sel
0%Tue 1/23/01Tue 1/23/011 day
Verify M&C manager robustness - Spectrometer
100%Fri 3/2/01Tue 3/6/013 days
Measure Spectrometer bandpass on CW signal - low speed
20%Fri 4/20/01Fri 5/4/015 days
Measure Spectrometer bandpass on CW signal - high speed
19%Mon 7/2/01Thu 7/12/013 days
Measure Spectrometer bandpass on CW signal - 9-level
3%Tue 7/3/01Mon 7/16/012 days
Implement Spectrometer pulsar mode
100%Fri 7/6/01Fri 7/13/015 days
Verify M&C manager robustness - LO1 Counter
0%Thu 3/29/01Mon 4/2/012 days
Verify M&C manager robustness - Holography
0%Thu 2/1/01Fri 2/2/012 days
Measure Holography phase stability on CW signal
0%Thu 2/8/01Thu 2/8/011 day
Verify 40-52 GHz M&C manager
0%Mon 4/9/01Tue 4/10/011.5 days
Implement spectral Line - SP
50%Thu 3/8/01Wed 3/28/015 days
Implement pulsar - SP
0%Tue 6/19/01Tue 6/26/015 days
Verify PF2 M&C manager
0%Tue 6/26/01Tue 6/26/011 day
Verify ephemeredes calculations
50%Wed 1/3/01Tue 1/9/015 days
Verify refraction calculations
50%Tue 1/9/01Mon 1/22/015 days
Verify proper use of pointing coefficients
100%Mon 1/15/01Mon 1/15/011 day
Determine cross scans optimum parameters(f)
0%Tue 2/13/01Wed 2/14/010.5 days
Determine focus scans optimum parameters(f)
0%Wed 2/14/01Thu 2/15/010.5 days
Determine 5-point optimum parameters(f)
0%Thu 3/29/01Thu 3/29/010.5 days
Determine OTF optimum mapping parameters
0%Thu 6/21/01Thu 6/21/010.5 days
Determine beam-switching parameters
0%Tue 6/26/01Wed 6/27/010.5 days
Determine polarization switching parameters
0%Wed 6/27/01Thu 6/28/010.5 days
Verify continuum tracking observing script
100%Tue 1/23/01Tue 1/23/011 day
Implement and verify continuum cross-scans observing script
100%Wed 1/24/01Wed 1/24/011 day
Implement and verify PF and Greg. focus tracking script
25%Thu 1/18/01Tue 2/13/012 days
Implement and verify continuum OTF mapping observing script
74%Fri 2/9/01Fri 2/16/012 days
Implement and verify continuum beam-switching observing script
0%Wed 2/21/01Wed 2/21/011 day
Implement and verify continuum polarization-switching observing script
0%Tue 2/20/01Tue 2/20/011 day
Implement and verify continuum on-off observing script
0%Fri 6/29/01Mon 7/2/010.5 days
Implement and verify continuum 5-point observing script
0%Mon 7/2/01Mon 7/2/010.5 days
Implement and verify continuum grid mapping observing script
0%Fri 7/13/01Mon 7/16/011 day
Verify line tracking observing script
100%Mon 4/30/01Mon 4/30/011 day
Implement and verify line beam-switching observing script
0%Wed 7/18/01Wed 7/18/010.5 days
Implement and verify line polarization-switching observing script
0%Wed 7/18/01Thu 7/19/010.5 days
Implement and verify line cross-scan observing script
0%Thu 7/19/01Fri 7/20/011 day
Implement and verify line 5-point observing script
0%Thu 7/19/01Fri 7/20/011 day
Implement and verify line OTF mapping observing script
0%Thu 9/20/01Fri 9/21/012 days
Implement and verify line Grid mapping observing script
0%Mon 9/24/01Mon 9/24/011 day
Implement Doppler tracking algorithm
0%Tue 5/22/01Tue 5/29/015 days
Verify Doppler tracking on a test CW source
0%Wed 5/30/01Thu 5/31/012 days
Implement and verify OTF holographic script
0%Fri 2/23/01Mon 2/26/012 days
Implement and verify GO I.F./ L.O. routing
0%Wed 5/2/01Wed 5/9/015 days
Pulsar observing techniques
0%Tue 6/5/01Tue 6/12/015 days
VLBI observing techniques
0%Wed 4/4/01Tue 5/1/0120 days
Verify Aips++ DCR filler
100%Thu 1/4/01Thu 1/4/011 day
Verify Holography Filler
0%Tue 4/3/01Tue 4/3/011 day
Implement actuator offset routine
0%Thu 2/1/01Wed 2/7/015 days
Verify Aips++ Spectrometer fillers
0%Tue 4/10/01Fri 4/13/013 days
Verify Aips++ Spectral Processor filler
15%Mon 5/7/01Tue 5/8/012 days
Measure PF focus Track
100%Wed 2/28/01Thu 3/1/012 days
Determine astronomically PF Xt(El), Y(El)
80%Thu 3/8/01Mon 7/9/015 days
Measure low-freq. Greg. focus track
100%Fri 7/27/01Mon 7/30/012 days
Determine low-freq. Greg. Xt(El), Y(El)
100%Wed 8/1/01Fri 8/3/013 days
Measure high freq. Greg focus track
0%Fri 10/26/01Mon 10/29/010.75 days
Determine high-freq. Greg. Xt(El), Y(El), and Zt(El)
0%Tue 10/30/01Thu 11/1/012 days
Determine Greg. Holography Xt(El). Y(El), and Zt(El)
0%Wed 10/24/01Fri 10/26/013 days
Determine telescope acceleration
100%Thu 2/1/01Thu 2/1/011 day
Determine settling time
0%Mon 2/5/01Mon 2/5/011 day
Observations of stars
0%Mon 3/12/01Mon 3/26/0110 days
Measure optical tracking stability
0%Thu 3/22/01Fri 3/23/012 days
Determine optical All-sky coefficients
0%Mon 3/26/01Mon 4/2/015 days
Determine Optical/Radio offsets
0%Mon 4/2/01Wed 4/4/012 days
Measure PF tracking stability
100%Tue 7/17/01Tue 7/17/011 day
Measure PF short-term stability
100%Wed 7/18/01Wed 7/18/011 day
Perform PF all-sky map
100%Thu 8/2/01Fri 8/3/012 days
Determine PF all-sky coefficients
50%Thu 8/9/01Wed 8/15/015 days
Verify PF all-sky coefficients
0%Thu 8/16/01Thu 8/16/011 day
Measure Greg. low freq. tracking stability
100%Mon 8/20/01Mon 8/20/011 day
Measure Greg low freq. short-term stability
100%Tue 8/21/01Tue 8/21/011 day
Perform Greg low freq. all-sky map
100%Wed 8/22/01Wed 8/22/011 day
Determine Greg low freq. all-sky coefficients
100%Mon 8/27/01Fri 8/31/015 days
Verify Greg low freq. all-sky coefficients
100%Tue 9/4/01Tue 9/4/011 day
Measure Greg high freq. tracking stability
0%Thu 11/1/01Fri 11/2/010.75 days
Measure Greg high freq. short-term stability
0%Mon 11/5/01Mon 11/5/010.75 days
Perform Greg high freq. all-sky map
0%Fri 11/16/01Fri 11/16/010.5 days
Determine Greg high freq. all-sky coefficients
0%Mon 11/19/01Thu 11/22/013 days
Verify Greg high freq. all-sky coefficients
0%Thu 11/22/01Fri 11/23/011 day
Determine actuator motions from photogrammetry map
80%Thu 1/25/01Wed 1/31/015 days
Measure 12 GHz photogrammetry efficiency pre- measurements
0%Thu 9/6/01Thu 9/6/011 day
Measure 12-GHz photogrammetry efficiency improvement
0%Fri 9/21/01Fri 9/21/011 day
Make Greg. high-resolution map near rigging angle
0%Mon 9/24/01Fri 9/28/015 days
Make Greg. Low-resolution maps at various El
0%Tue 10/2/01Mon 10/8/015 days
Determine actuator motions from holographic map
0%Tue 10/16/01Mon 10/22/015 days
Measure Greg 12 GHz Holog efficiency pre- measurements
0%Fri 10/12/01Fri 10/12/010.5 days
Measure Greg 12-GHz Holog efficiency improvement
0%Tue 10/23/01Tue 10/23/010.5 days
Make PF High-resolution map near rigging angle
0%Thu 4/25/02Tue 4/30/023 days
Make PF Low-resolution maps at various El
0%Tue 4/30/02Fri 5/3/023 days
Measure PF 12 GHz FE efficiency pre-measurements
0%Mon 10/15/01Mon 10/15/010.5 days
Measure PF 12-GHz FE efficiency improvement
0%Mon 10/15/01Mon 10/15/010.5 days
Measure 8-10 GHz efficiencies
0%Wed 10/24/01Thu 10/25/011.5 days
Measure 12-18 GHz efficiencies
0%Mon 10/29/01Tue 10/30/011 day
Measure 18-26 GHz efficiencies
0%Fri 11/2/01Mon 11/5/011 day
Measure 40-52 GHz efficiencies
0%Mon 11/19/01Wed 11/21/012 days
Measure 0.3 - 8 GHz efficiencies
40%Tue 11/6/01Tue 11/13/015 days
Measure scattering pattern - 12 GHz
0%Fri 11/23/01Mon 11/26/011 day
Measure scattering pattern - 26 GHz
0%Mon 11/26/01Mon 11/26/010.5 days
Measure scattering pattern - 50 GHz
0%Mon 11/26/01Mon 11/26/010.5 days
Measure 800 MHz outer sidelobes
0%Tue 11/27/01Tue 12/4/015 days
Measure 1 GHz outer sidelobes
0%Mon 12/3/01Tue 12/4/012 days
Measure 12 GHz outer sidelobes
0%Mon 12/10/01Tue 12/11/012 days
Demonstrate Continuum OTF mapping
100%Mon 9/10/01Tue 9/11/011.5 days
Demonstrate line sensitivity - Strong and weak spectral lines
0%Mon 8/20/01Tue 8/21/012 days
Demonstrate wide-weak spectral line sensitivity
0%Mon 9/10/01Tue 9/11/012 days
Demonstrate spectral line OTF mapping
0%Fri 8/31/01Thu 9/6/014 days
Determine 800 MHz axial focus curve (f,pol)
0%Tue 7/3/01Thu 7/5/012 days
Measure 800 MHz collimation
0%Mon 12/17/01Tue 12/18/012 days
Observe 800 MHz gain calibrators(f,pol)
0%Wed 12/19/01Thu 12/20/012 days
Measure 800 MHz inner beam maps(f,pol)
56%Thu 12/27/01Mon 12/31/012 days
Measure 800 MHz bandpass(f.pol) and baselines(f,pol)
0%Mon 12/24/01Wed 12/26/013 days
Measure 800 MHz beam squint(f)
88%Tue 1/1/02Thu 1/3/022 days
Determine 800 MHz polarization hybrid settings(f)
0%Tue 12/25/01Wed 12/26/012 days
Determine 800 MHz Tcal(f,pol) and Tsys(f,pol)
50%Mon 1/7/02Mon 1/14/025 days
Determine 1-2 GHz axial focus curve (f,pol)
0%Mon 12/31/01Mon 12/31/011 day
Measure 1-2 GHz MHz collimation
0%Thu 12/13/01Fri 12/14/011 day
Observe 1-2 GHz gain calibrators(f,pol)
0%Thu 1/3/02Mon 1/7/022 days
Measure 1-2 GHz inner beam maps(f,pol)
0%Mon 1/7/02Mon 1/7/021 day
Measure 1-2 GHz bandpass(f.pol) and baselines(f,pol)
0%Tue 1/8/02Tue 1/8/021 day
Measure 1-2 GHz beam squint(f)
0%Thu 1/10/02Thu 1/10/021 day
Determine 1-2 GHz polarization hybrid settings(f)
0%Fri 1/11/02Fri 1/11/021 day
Determine 1-2 GHz Tcal(f,pol) and Tsys(f,pol)
0%Mon 1/14/02Wed 1/16/023 days
Determine 1-2 GHz atmospheric Tau(f)
0%Mon 1/14/02Thu 1/17/023 days
Determine 12-18 GHz axial focus curve (f,pol)
0%Thu 1/17/02Thu 1/17/021 day
Measure 12-18 GHz MHz collimation
0%Fri 1/18/02Fri 1/18/020.5 days
Determine 12-18 GHz beam-switching blanking
0%Fri 12/7/01Fri 12/7/010.5 days
Observe 12-18 GHz gain calibrators(f,pol)
0%Mon 1/21/02Mon 1/21/021 day
Measure 12-18 GHz inner beam maps(f,pol)
0%Mon 1/21/02Mon 1/21/021 day
Measure 12-18 GHz bandpass(f.pol) and baselines(f,pol)
0%Tue 1/22/02Tue 1/22/021 day
Measure 12-18 GHz beam squint(f)
0%Wed 1/23/02Wed 1/23/021 day
Determine 12-18 GHz Tcal(f,pol) and Tsys(f,pol)
0%Thu 1/24/02Thu 1/24/021 day
Determine 12-18 GHz atmospheric Tau(f)
0%Thu 1/24/02Thu 1/24/021 day
Determine 40-52 GHz axial focus curve (f,pol)
0%Fri 1/25/02Fri 1/25/021 day
Measure 40-52 GHz MHz collimation
0%Mon 1/28/02Mon 1/28/021 day
Determine 40-52 GHz beam-switching/tertiary blanking
0%Mon 1/28/02Mon 1/28/020.5 days
Observe 40-52 GHz gain calibrators(f,pol)
0%Thu 1/31/02Thu 1/31/021 day
Measure 40-52 GHz inner beam maps(f,pol)
0%Mon 2/4/02Mon 2/4/021 day
Measure 40-52 GHz bandpass(f.pol) and baselines(f,pol)
0%Tue 2/5/02Tue 2/5/021 day
Measure 40-52 GHz beam squint(f)
0%Thu 2/7/02Thu 2/7/021 day
Determine 40-52 GHz Tcal(f,pol) and Tsys(f,pol)
0%Fri 2/8/02Mon 2/11/022 days
Determine 40-52 GHz atmospheric Tau(f)
0%Fri 2/8/02Mon 2/11/022 days
Determine 300 MHz axial focus curve (f,pol)
0%Wed 2/20/02Wed 2/20/020.5 days
Measure 300 MHz collimation
0%Thu 2/21/02Thu 2/21/020.5 days
Observe 300 MHz gain calibrators(f,pol)
0%Fri 2/22/02Fri 2/22/021 day
Measure 300 MHz inner beam maps(f,pol)
0%Mon 2/25/02Mon 2/25/021 day
Measure 300 MHz bandpass(f.pol) and baselines(f,pol)
0%Mon 2/25/02Mon 2/25/021 day
Measure 300 MHz beam squint(f)
0%Tue 2/26/02Tue 2/26/021 day
Determine 300 MHz polarization hybrid settings(f)
0%Wed 2/27/02Wed 2/27/021 day
Determine 300 MHz Tcal(f,pol) and Tsys(f,pol)
0%Thu 2/28/02Thu 2/28/021 day
Determine 2-3 GHz axial focus curve (f,pol)
0%Thu 2/28/02Thu 2/28/020.5 days
Measure 2-3 GHz MHz collimation
0%Fri 3/1/02Fri 3/1/020.5 days
Observe 2-3 GHz gain calibrators(f,pol)
0%Mon 3/11/02Mon 3/11/021 day
Measure 2-3 GHz inner beam maps(f,pol)
20%Mon 3/11/02Mon 3/11/021 day
Measure 2-3 GHz bandpass(f.pol) and baselines(f,pol)
0%Mon 3/4/02Mon 3/4/021 day
Measure 2-3 GHz beam squint(f)
100%Wed 3/13/02Wed 3/13/021 day
Determine 2-3 GHz polarization hybrid settings(f)
0%Mon 3/4/02Mon 3/4/021 day
Determine 2-3 GHz Tcal(f,pol) and Tsys(f,pol)
50%Fri 3/15/02Fri 3/15/021 day
Determine 2-3 GHz atmospheric Tau(f)
50%Fri 3/15/02Fri 3/15/021 day
Determine 4-6 GHz axial focus curve (f,pol)
0%Tue 3/5/02Tue 3/5/020.5 days
Measure 4-6 GHz MHz collimation
0%Wed 3/6/02Wed 3/6/020.5 days
Observe 4-6 GHz gain calibrators(f,pol)
0%Thu 3/7/02Thu 3/7/021 day
Measure 4-6 GHz inner beam maps(f,pol)
0%Fri 3/8/02Fri 3/8/021 day
Measure 4-6 GHz bandpass(f.pol) and baselines(f,pol)
0%Tue 3/12/02Tue 3/12/021 day
Measure 4-6 GHz beam squint(f)
0%Thu 3/14/02Thu 3/14/021 day
Determine 4-6 GHz polarization hybrid settings(f)
0%Mon 3/18/02Mon 3/18/021 day
Determine 4-6 GHz Tcal(f,pol) and Tsys(f,pol)
0%Tue 3/19/02Tue 3/19/021 day
Determine 4-6 GHz atmospheric Tau(f)
0%Tue 3/19/02Tue 3/19/021 day
Determine 8-10 GHz axial focus curve (f,pol)
0%Wed 3/20/02Wed 3/20/020.5 days
Measure 8-10 GHz MHz collimation
0%Thu 3/21/02Thu 3/21/020.5 days
Observe 8-10 GHz gain calibrators(f,pol)
0%Fri 3/22/02Fri 3/22/021 day
Measure 8-10 GHz inner beam maps(f,pol)
0%Mon 3/25/02Mon 3/25/021 day
Measure 8-10 GHz bandpass(f.pol) and baselines(f,pol)
0%Mon 3/25/02Mon 3/25/021 day
Measure 8-10 GHz beam squint(f)
0%Tue 3/26/02Tue 3/26/021 day
Determine 8-10 GHz Tcal(f,pol) and Tsys(f,pol)
0%Wed 3/27/02Wed 3/27/021 day
Determine 8-10 GHz atmospheric Tau(f)
0%Wed 3/27/02Wed 3/27/021 day
Determine 18-26 GHz axial focus curve (f,pol)
0%Thu 3/28/02Thu 3/28/021 day
Measure 18-26 GHz MHz collimation
0%Fri 3/29/02Fri 3/29/021 day
Determine 18-26 GHz beam-switching blanking
0%Mon 4/1/02Mon 4/1/021 day
Observe 18-26 GHz gain calibrators(f,pol)
0%Tue 4/2/02Tue 4/2/021 day
Measure 18-26 GHz inner beam maps(f,pol)
0%Thu 4/4/02Thu 4/4/021 day
Measure 18-26 GHz bandpass(f.pol) and baselines(f,pol)
0%Fri 4/5/02Fri 4/5/021 day
Measure 18-26 GHz beam squint(f)
0%Mon 4/8/02Mon 4/8/021 day
Determine 18-26 GHz Tcal(f,pol) and Tsys(f,pol)
0%Tue 4/9/02Wed 4/10/022 days
Determine 18-26 GHz atmospheric Tau(f)
0%Tue 4/9/02Wed 4/10/022 days
Determine PF2 axial focus curve (f,pol)
0%Mon 4/1/02Mon 4/1/020.5 days
Measure PF2 MHz collimation
0%Mon 4/8/02Mon 4/8/020.5 days
Observe PF2 gain calibrators(f,pol)
0%Thu 4/11/02Thu 4/11/021 day
Measure PF2 inner beam maps(f,pol)
0%Fri 4/12/02Fri 4/12/021 day
Measure PF2 bandpass(f.pol) and baselines(f,pol)
0%Mon 4/15/02Mon 4/15/021 day
Measure PF2 beam squint(f)
0%Mon 4/15/02Mon 4/15/021 day
Determine PF2 polarization hybrid settings(f)
0%Tue 4/16/02Tue 4/16/021 day
Determine PF2 Tcal(f,pol) and Tsys(f,pol)
0%Wed 4/17/02Wed 4/17/021 day
Specify VLBI software interfaces
100%Fri 3/16/01Wed 3/21/014 days
Upgrade VLBA software to current version
94%Tue 4/24/01Wed 5/2/014 days
Design VLBI software communication
94%Fri 5/18/01Thu 5/24/014 days
Code and test VLBI software
82%Fri 5/25/01Fri 6/1/014 days
Specify new S2 communication software
0%Tue 4/16/02Fri 4/19/024 days
Implement S2 system with GBT
0%Tue 4/23/02Fri 4/26/024 days
Upgrade VLBA formatter for 2-recorders
0%Thu 4/18/02Tue 4/23/024 days
Complete optical telescope hardware
0%Wed 1/3/01Thu 1/4/012 days
Complete optical telescope software
0%Thu 1/25/01Wed 1/31/015 days
Measure Hol Greg. pointing collimation
0%Mon 9/17/01Mon 9/17/010.5 days
Determine Hol. Greg. axial focus curve
0%Mon 9/17/01Mon 9/17/010.5 days
Measure Hol. Greg. phase stability on calibrator
0%Tue 9/18/01Tue 9/18/010.75 days
Measure Hol PF pointing collimation
0%Mon 4/22/02Mon 4/22/020.5 days
Determine Hol PF axial focus curve
0%Wed 4/24/02Wed 4/24/020.5 days
Measure Hol PF phase stability on calibrator
0%Thu 4/25/02Thu 4/25/020.5 days
Demonstrate pulsar observing using the Spectrometer
0%Wed 10/17/01Mon 10/22/014 days
Demonstrate pulsar observing using the Spectral Processor
0%Mon 2/18/02Thu 2/21/024 days
Measure Green Bank ties
0%Thu 9/13/01Fri 9/14/012 days
Demonstrate control of GBT for VLBA
0%Mon 10/15/01Tue 10/16/012 days
Demonstrate S2 VLB recording
0%Thu 2/14/02Fri 2/15/022 days
Demonstrate VLB dual-recording capabilities
0%Fri 2/15/02Mon 2/18/022 days
Demonstrate spectral lines with the Spectral Processor in RFI environment
0%Wed 9/12/01Fri 9/14/013 days
Determine position-switched parameters
0%Fri 6/22/01Fri 6/22/010.5 days
Determine frequency-switching parameters
0%Mon 6/25/01Mon 6/25/010.5 days
Determine grid optimum mapping parameters
0%Thu 6/28/01Fri 6/29/010.5 days
Implement and verify line position-switching observing script
0%Thu 2/22/01Thu 2/22/011 day
Implement and verify line frequency-switching observing script
0%Mon 4/2/01Mon 4/2/010.5 days
Determine 800 MHz polarization-switching blanking
0%Thu 10/25/01Thu 10/25/010.5 days
Determine 1-2 GHz polarization-switching blanking
0%Mon 12/31/01Mon 12/31/010.5 days
Determine 2-3 GHz polarization-switching blanking
0%Wed 1/30/02Wed 1/30/020.5 days
Determine 4-6 GHz polarization-switching blanking
0%Tue 2/12/02Tue 2/12/020.5 days
Determine PF2 polarization-switching blanking
0%Wed 2/13/02Wed 2/13/020.5 days
Determine 300 MHz polarization-switching blanking
0%Tue 1/29/02Tue 1/29/020.5 days
Test LO1 manager
100%Fri 1/12/01Fri 1/12/011 day
Check LO1 frequency
100%Thu 1/11/01Thu 1/11/011 day
Test I.F. manager
100%Tue 1/16/01Wed 1/17/011 day
Test I.F. hardware
100%Fri 1/12/01Mon 1/15/011 day
Measure clock & switching-signal delays
80%Mon 1/15/01Mon 1/15/011 day
Implement acceptance of pointing results from Aips++
100%Fri 1/26/01Fri 1/26/011 day
Implement cross-scan pointing data reduction
100%Tue 1/9/01Tue 1/9/011 day
Implement 1-d focus-curve fitting
0%Fri 1/5/01Fri 1/5/011 day
Implement 2-d focus curve fitting
0%Mon 1/8/01Tue 1/9/012 days
Implement real-time data display and quick reduction
0%Thu 1/11/01Thu 1/11/011 day
Implement all-sky pointing data reduction
100%Thu 1/11/01Thu 1/11/011 day
Implement Tcal and Tsys data reduction
0%Mon 1/15/01Mon 1/15/011 day
Implement atmospheric model fitting
0%Tue 1/16/01Tue 1/16/011 day
Implement continuum OTF mapping data reduction
0%Thu 1/18/01Fri 1/19/012 days
Implement continuum polarization data reduction
0%Thu 1/18/01Fri 1/19/012 days
Implement beam-switching data reduction
0%Thu 1/18/01Fri 1/19/012 days
Implement Amp/phase, Re/I'm, Illum/Offset plotting tools
0%Tue 1/23/01Tue 1/23/011 day
Implement real-time data display
0%Tue 1/23/01Tue 1/23/011 day
Implement 2-d Amp/phase holographic regridding
0%Tue 1/23/01Tue 1/23/011 day
Implement Step 1 instrumental corrections
0%Thu 1/25/01Thu 1/25/011 day
Implement 2-d IFFT routines
0%Thu 1/25/01Thu 1/25/010.5 days
Implement Step 2 instrumental corrections
0%Fri 1/26/01Fri 1/26/011 day
Implement phase-fitting routine
0%Thu 2/1/01Fri 2/2/012 days
Implement real-time data display
0%Thu 2/22/01Thu 2/22/011 day
Implement Doppler-tracking regridding
0%Thu 2/22/01Thu 2/22/011 day
Implement continuum grid mapping data reduction
0%Thu 2/22/01Thu 2/22/011 day
Implement 5-point continuum pointing data reduction
0%Wed 7/18/01Wed 7/18/011 day
Implement On-Off data reduction
0%Wed 7/18/01Wed 7/18/011 day
Implement multi-purpose continuum plotting tools
0%Thu 1/4/01Thu 1/4/011 day
Implement 1-d continuum OTF regridding
0%Thu 1/4/01Thu 1/4/011 day
Implement 2-d continuum regridding
0%Tue 1/16/01Tue 1/16/011 day
Implement multi-purpose spectral-line plotting tools
0%Fri 2/2/01Fri 2/2/011 day
Implement 5-point spectral-line pointing data reduction
0%Wed 7/18/01Wed 7/18/011 day
Implement 3-d spectral-line regridding
0%Thu 7/19/01Thu 7/19/011 day
Implement spectral-line grid mapping data reduction
0%Fri 7/20/01Fri 7/20/011 day
Implement spectral-line OTF mapping data reduction
0%Fri 7/20/01Fri 7/20/011 day
Implement polarization data reduction
0%Tue 9/18/01Tue 9/18/011 day
Measure Prime Focus spillover(El)
0%Thu 7/19/01Tue 7/24/014 days
Measure Gregorian spillover(El)
50%Mon 8/27/01Thu 8/30/014 days
Measure baselines pre spoiler installation
100%Thu 5/10/01Wed 5/16/014 days
Measure baselines post spoiler installation
0%Wed 5/16/01Mon 5/21/014 days
Measure baseline shapes -- Day vs. Night
25%Mon 6/4/01Thu 6/7/014 days
Examine I.F. bandpass for birdies
0%Wed 6/13/01Tue 6/19/014 days
Measure RFI 300 MHz - 5 GHz
18%Mon 6/11/01Wed 6/20/018 days
Demonstration of zero-space flux measurements for VLA data
0%Fri 12/14/01Thu 12/20/014 days
Verify observing catalogs/tables
100%Tue 1/2/01Tue 1/2/011 day
Measure low-freq. Greg. plate scale
100%Wed 8/1/01Wed 8/1/011 day
Measure high-freq. Greg. plate scale
0%Mon 8/13/01Mon 8/13/011 day
Prepare for and move actuators according to photogrammetry results
0%Tue 9/18/01Wed 9/19/012 days
Determine whether or not to use Prime Focus maps for surface setting
0%Fri 10/26/01Thu 11/1/014 days
Servo - Prime Focus
0%Thu 7/5/01Thu 7/5/011 day
Servo - actuator/turret low freq.
100%Mon 7/23/01Thu 7/26/012.5 days
Servo - actuator/turret High Freq.
0%Tue 8/7/01Thu 8/9/013 days
Synthesize focus determinations from all methods
0%Mon 8/6/01Wed 8/8/013 days
Verification of high-freq. Greg. focus coefficients
0%Tue 8/14/01Fri 8/17/014 days
GBT
15%Thu 2/1/01Sun 5/5/02769 days
Measure PF focus Track
100%Wed 2/28/01Mon 3/5/0115 days
Measure low-freq. Greg. focus track
100%Thu 7/26/01Tue 7/31/0115 days
Measure high freq. Greg focus track
0%Fri 10/26/01Mon 10/29/019 days
Determine telescope acceleration
75%Thu 2/1/01Sat 2/3/016 days
Determine settling time
88%Sat 2/3/01Mon 2/5/016 days
Observations of stars
0%Mon 3/12/01Thu 3/15/019 days
Measure optical tracking stability
0%Thu 3/22/01Sat 3/24/016 days
Determine Optical/Radio offsets
0%Sun 7/1/01Tue 7/3/016 days
Measure PF tracking stability
80%Tue 7/17/01Wed 7/18/013 days
Measure PF short-term stability
80%Wed 7/18/01Thu 7/19/013 days
Perform PF all-sky map
50%Wed 8/1/01Mon 8/6/0115 days
Verify PF all-sky coefficients
0%Wed 8/15/01Fri 8/17/016 days
Measure Greg. low freq. tracking stability
100%Fri 8/17/01Sat 8/18/013 days
Measure Greg low freq. short-term stability
100%Mon 8/20/01Tue 8/21/013 days
Perform Greg low freq. all-sky map
100%Tue 8/21/01Sun 8/26/0115 days
Verify Greg low freq. all-sky coefficients
100%Sat 9/1/01Sun 9/2/013 days
Measure Greg high freq. short-term stability
0%Sat 11/3/01Sun 11/4/013 days
Perform Greg high freq. all-sky map
0%Fri 11/16/01Mon 11/19/019 days
Verify Greg high freq. all-sky coefficients
0%Thu 11/22/01Fri 11/23/013 days
Measure 12 GHz photogrammetry efficiency pre- measurements
0%Wed 9/5/01Thu 9/6/013 days
Measure 12-GHz photogrammetry efficiency improvement
0%Thu 9/20/01Fri 9/21/013 days
Make Greg. high-resolution map near rigging angle
0%Fri 9/21/01Mon 10/1/0130 days
Make Greg. Low-resolution maps at various El
0%Mon 10/1/01Thu 10/11/0130 days
Measure Greg 12 GHz Holog efficiency pre- measurements
0%Thu 10/11/01Fri 10/12/013 days
Measure Greg 12-GHz Holog efficiency improvement
0%Mon 10/22/01Tue 10/23/013 days
Make PF High-resolution map near rigging angle
0%Thu 4/25/02Tue 4/30/0215 days
Make PF Low-resolution maps at various El
0%Tue 4/30/02Sun 5/5/0215 days
Measure PF 12 GHz FE efficiency pre-measurements
0%Fri 10/12/01Sat 10/13/013 days
Measure PF 12-GHz FE efficiency improvement
0%Mon 10/15/01Tue 10/16/013 days
Measure 8-10 GHz efficiencies
0%Tue 10/23/01Wed 10/24/013 days
Measure 12-18 GHz efficiencies
0%Mon 10/29/01Tue 10/30/013 days
Measure 18-26 GHz efficiencies
0%Fri 11/2/01Sat 11/3/013 days
Measure 40-52 GHz efficiencies
0%Mon 11/19/01Thu 11/22/019 days
Measure 0.3 - 8 GHz efficiencies
20%Tue 11/6/01Fri 11/16/0130 days
Measure scattering pattern - 12 GHz
0%Fri 11/23/01Sat 11/24/013 days
Measure scattering pattern - 26 GHz
0%Sat 11/24/01Sun 11/25/013 days
Measure scattering pattern - 50 GHz
0%Mon 11/26/01Tue 11/27/013 days
Measure 800 MHz outer sidelobes
0%Tue 11/27/01Sun 12/2/0115 days
Measure 1 GHz outer sidelobes
0%Sun 12/2/01Fri 12/7/0115 days
Measure 12 GHz outer sidelobes
0%Sat 12/8/01Thu 12/13/0115 days
Demonstrate Continuum OTF mapping
100%Sat 9/8/01Mon 9/10/016 days
Demonstrate line sensitivity - Strong and weak spectral lines
0%Sat 8/18/01Mon 8/20/016 days
Demonstrate wide-weak spectral line sensitivity
0%Mon 9/10/01Wed 9/12/016 days
Demonstrate spectral line OTF mapping
0%Thu 8/30/01Sat 9/1/016 days
Determine 800 MHz axial focus curve (f,pol)
0%Tue 7/3/01Wed 7/4/013 days
Measure 800 MHz collimation
0%Sun 12/16/01Mon 12/17/013 days
Observe 800 MHz gain calibrators(f,pol)
0%Tue 12/18/01Fri 12/21/019 days
Measure 800 MHz inner beam maps(f,pol)
52%Thu 12/27/01Sat 12/29/016 days
Measure 800 MHz bandpass(f.pol) and baselines(f,pol)
0%Fri 12/21/01Mon 12/24/019 days
Measure 800 MHz beam squint(f)
80%Tue 1/1/02Thu 1/3/026 days
Determine 800 MHz polarization hybrid settings(f)
0%Mon 12/24/01Wed 12/26/016 days
Determine 1-2 GHz axial focus curve (f,pol)
0%Sat 12/29/01Sun 12/30/013 days
Measure 1-2 GHz MHz collimation
0%Thu 12/13/01Fri 12/14/013 days
Observe 1-2 GHz gain calibrators(f,pol)
0%Thu 1/3/02Sat 1/5/026 days
Measure 1-2 GHz inner beam maps(f,pol)
0%Sat 1/5/02Mon 1/7/026 days
Measure 1-2 GHz bandpass(f.pol) and baselines(f,pol)
0%Tue 1/8/02Thu 1/10/026 days
Measure 1-2 GHz beam squint(f)
0%Thu 1/10/02Fri 1/11/023 days
Determine 1-2 GHz polarization hybrid settings(f)
0%Fri 1/11/02Sat 1/12/023 days
Determine 12-18 GHz axial focus curve (f,pol)
0%Thu 1/17/02Fri 1/18/023 days
Measure 12-18 GHz MHz collimation
0%Fri 1/18/02Sat 1/19/023 days
Determine 12-18 GHz beam-switching blanking
0%Fri 12/7/01Sat 12/8/013 days
Observe 12-18 GHz gain calibrators(f,pol)
0%Sat 1/19/02Sun 1/20/023 days
Measure 12-18 GHz inner beam maps(f,pol)
0%Sun 1/20/02Mon 1/21/023 days
Measure 12-18 GHz bandpass(f.pol) and baselines(f,pol)
0%Tue 1/22/02Wed 1/23/023 days
Measure 12-18 GHz beam squint(f)
0%Wed 1/23/02Thu 1/24/023 days
Determine 40-52 GHz axial focus curve (f,pol)
0%Fri 1/25/02Sun 1/27/026 days
Measure 40-52 GHz MHz collimation
0%Sun 1/27/02Mon 1/28/023 days
Determine 40-52 GHz beam-switching/tertiary blanking
0%Mon 1/28/02Tue 1/29/023 days
Observe 40-52 GHz gain calibrators(f,pol)
0%Thu 1/31/02Sun 2/3/029 days
Measure 40-52 GHz inner beam maps(f,pol)
0%Sun 2/3/02Tue 2/5/026 days
Measure 40-52 GHz bandpass(f.pol) and baselines(f,pol)
0%Tue 2/5/02Thu 2/7/026 days
Measure 40-52 GHz beam squint(f)
0%Thu 2/7/02Fri 2/8/023 days
Determine 300 MHz axial focus curve (f,pol)
0%Wed 2/20/02Thu 2/21/023 days
Measure 300 MHz collimation
0%Thu 2/21/02Fri 2/22/023 days
Observe 300 MHz gain calibrators(f,pol)
0%Fri 2/22/02Sat 2/23/023 days
Measure 300 MHz inner beam maps(f,pol)
0%Sat 2/23/02Sun 2/24/023 days
Measure 300 MHz bandpass(f.pol) and baselines(f,pol)
0%Mon 2/25/02Tue 2/26/023 days
Measure 300 MHz beam squint(f)
0%Tue 2/26/02Wed 2/27/023 days
Determine 300 MHz polarization hybrid settings(f)
0%Wed 2/27/02Thu 2/28/023 days
Determine 2-3 GHz axial focus curve (f,pol)
0%Thu 2/28/02Fri 3/1/023 days
Measure 2-3 GHz MHz collimation
0%Fri 3/1/02Sat 3/2/023 days
Observe 2-3 GHz gain calibrators(f,pol)
67%Sat 3/9/02Sun 3/10/023 days
Measure 2-3 GHz inner beam maps(f,pol)
100%Sun 3/10/02Mon 3/11/023 days
Measure 2-3 GHz bandpass(f.pol) and baselines(f,pol)
0%Sat 3/2/02Sun 3/3/023 days
Measure 2-3 GHz beam squint(f)
80%Wed 3/13/02Thu 3/14/023 days
Determine 2-3 GHz polarization hybrid settings(f)
0%Sun 3/3/02Mon 3/4/023 days
Determine 4-6 GHz axial focus curve (f,pol)
0%Tue 3/5/02Wed 3/6/023 days
Measure 4-6 GHz MHz collimation
0%Wed 3/6/02Thu 3/7/023 days
Observe 4-6 GHz gain calibrators(f,pol)
0%Thu 3/7/02Fri 3/8/023 days
Measure 4-6 GHz inner beam maps(f,pol)
0%Fri 3/8/02Sat 3/9/023 days
Measure 4-6 GHz bandpass(f.pol) and baselines(f,pol)
0%Tue 3/12/02Wed 3/13/023 days
Measure 4-6 GHz beam squint(f)
0%Thu 3/14/02Fri 3/15/023 days
Determine 4-6 GHz polarization hybrid settings(f)
0%Mon 3/18/02Tue 3/19/023 days
Determine 8-10 GHz axial focus curve (f,pol)
0%Wed 3/20/02Thu 3/21/023 days
Measure 8-10 GHz MHz collimation
0%Thu 3/21/02Fri 3/22/023 days
Observe 8-10 GHz gain calibrators(f,pol)
0%Fri 3/22/02Sat 3/23/023 days
Measure 8-10 GHz inner beam maps(f,pol)
0%Sat 3/23/02Sun 3/24/023 days
Measure 8-10 GHz bandpass(f.pol) and baselines(f,pol)
0%Mon 3/25/02Tue 3/26/023 days
Measure 8-10 GHz beam squint(f)
0%Tue 3/26/02Wed 3/27/023 days
Determine 18-26 GHz axial focus curve (f,pol)
0%Thu 3/28/02Fri 3/29/023 days
Measure 18-26 GHz MHz collimation
0%Fri 3/29/02Sat 3/30/023 days
Determine 18-26 GHz beam-switching blanking
0%Sat 3/30/02Sun 3/31/023 days
Observe 18-26 GHz gain calibrators(f,pol)
0%Tue 4/2/02Thu 4/4/026 days
Measure 18-26 GHz inner beam maps(f,pol)
0%Thu 4/4/02Fri 4/5/023 days
Measure 18-26 GHz bandpass(f.pol) and baselines(f,pol)
0%Fri 4/5/02Sat 4/6/023 days
Measure 18-26 GHz beam squint(f)
0%Sat 4/6/02Sun 4/7/023 days
Determine PF2 axial focus curve (f,pol)
0%Mon 4/1/02Tue 4/2/023 days
Measure PF2 MHz collimation
0%Mon 4/8/02Tue 4/9/023 days
Observe PF2 gain calibrators(f,pol)
0%Thu 4/11/02Fri 4/12/023 days
Measure PF2 inner beam maps(f,pol)
0%Fri 4/12/02Sat 4/13/023 days
Measure PF2 bandpass(f.pol) and baselines(f,pol)
0%Sat 4/13/02Sun 4/14/023 days
Measure PF2 beam squint(f)
0%Mon 4/15/02Tue 4/16/023 days
Determine PF2 polarization hybrid settings(f)
0%Tue 4/16/02Wed 4/17/023 days
Metrology determination of pointing coefficients
0%Sat 7/7/01Tue 7/17/0115 days
Metrology determination of Greg. Xt(El,temp), Y(El,temp)
0%Thu 2/15/01Sun 2/25/0115 days
Measure Greg high freq. tracking stability
0%Thu 11/1/01Fri 11/2/013 days
Measure Hol Greg. pointing collimation
0%Mon 9/17/01Mon 9/17/011.5 days
Determine Hol. Greg. axial focus curve
0%Mon 9/17/01Tue 9/18/011.5 days
Measure Hol. Greg. phase stability on calibrator
0%Tue 9/18/01Tue 9/18/012 days
Measure Hol PF pointing collimation
0%Mon 4/22/02Mon 4/22/021 day
Determine Hol PF axial focus curve
0%Wed 4/24/02Wed 4/24/021.5 days
Measure Hol PF phase stability on calibrator
0%Wed 4/24/02Thu 4/25/022 days
Demonstrate pulsar observing using the Spectrometer
0%Tue 10/16/01Thu 10/18/016 days
Demonstrate pulsar observing using the Spectral Processor
0%Mon 2/18/02Wed 2/20/026 days
Measure Green Bank ties
0%Thu 9/13/01Fri 9/14/013 days
Demonstrate control of GBT for VLBA
0%Sat 10/13/01Sun 10/14/013 days
Demonstrate S2 VLB recording
0%Thu 2/14/02Fri 2/15/023 days
Demonstrate VLB dual-recording capabilities
0%Fri 2/15/02Sat 2/16/023 days
Demonstrate spectral lines with the Spectral Processor in RFI environment
0%Wed 9/12/01Thu 9/13/013 days
Determine 800 MHz polarization-switching blanking
0%Thu 10/25/01Fri 10/26/013 days
Determine 1-2 GHz polarization-switching blanking
0%Mon 12/31/01Tue 1/1/023 days
Determine 2-3 GHz polarization-switching blanking
0%Wed 1/30/02Thu 1/31/023 days
Determine 4-6 GHz polarization-switching blanking
0%Tue 2/12/02Wed 2/13/023 days
Determine PF2 polarization-switching blanking
0%Wed 2/13/02Thu 2/14/023 days
Determine 300 MHz polarization-switching blanking
0%Tue 1/29/02Wed 1/30/023 days
Measure Prime Focus spillover(El)
0%Thu 7/19/01Sat 7/21/016 days
Measure Gregorian spillover(El)
100%Sun 8/26/01Tue 8/28/016 days
Install spoilers
0%Thu 3/8/01Fri 3/9/013 days
Demonstration of zero-space flux measurements for VLA data
0%Fri 12/14/01Sun 12/16/016 days
Measure low-freq. Greg. plate scale
100%Tue 7/31/01Wed 8/1/013 days
Measure high-freq. Greg. plate scale
0%Sun 8/12/01Mon 8/13/013 days
Servo - Prime Focus
0%Wed 7/4/01Sat 7/7/019 days
Servo - actuator/turret low freq.
100%Mon 7/23/01Wed 7/25/016.5 days
Servo - actuator/turret High Freq.
0%Mon 8/6/01Thu 8/9/019 days
Verification of high-freq. Greg. focus coefficients
0%Mon 8/13/01Tue 8/14/013 days
Mockup
40%Tue 1/2/01Tue 4/23/02146 days
Measure baselines pre spoiler installation
100%Thu 5/10/01Sat 5/12/016 days
Measure baselines post spoiler installation
0%Wed 5/16/01Fri 5/18/016 days
Measure baseline shapes -- Day vs. Night
69%Sun 6/3/01Tue 6/5/016 days
Measure RFI 300 MHz - 5 GHz
72%Sat 6/9/01Wed 6/13/0112 days
DCR tests
100%Wed 1/10/01Wed 1/10/011 day
Test LO1 manager
100%Fri 1/12/01Fri 1/12/011 day
Check LO1 frequency
100%Thu 1/11/01Thu 1/11/011 day
Test I.F. manager
100%Tue 1/16/01Tue 1/16/011 day
Test I.F. hardware
100%Fri 1/12/01Sat 1/13/013 days
Test Switch Sig Sel
100%Fri 1/19/01Fri 1/19/011 day
Verify M&C manager robustness - Spectrometer
100%Fri 3/2/01Sat 3/3/013 days
Measure Spectrometer bandpass on CW signal - low speed
90%Fri 4/20/01Mon 4/30/015 days
Measure Spectrometer bandpass on CW signal - high speed
83%Mon 7/2/01Mon 7/9/013 days
Measure Spectrometer bandpass on CW signal - 9-level
98%Tue 7/3/01Thu 7/12/012 days
Verify M&C manager robustness - LO1 Counter
0%Thu 3/29/01Fri 3/30/012 days
Verify M&C manager robustness - Holography
0%Thu 2/1/01Fri 2/2/012 days
Measure Holography phase stability on CW signal
0%Thu 2/8/01Thu 2/8/011 day
Code and test VLBI software
100%Fri 5/25/01Sat 5/26/012 days
Implement S2 system with GBT
0%Mon 4/22/02Tue 4/23/021 day
Upgrade VLBA formatter for 2-recorders
0%Thu 4/18/02Fri 4/19/022 days
Measure clock & switching-signal delays
100%Sun 1/14/01Mon 1/15/011 day
Verify 40-52 GHz M&C manager
0%Sat 4/7/01Sat 4/7/011 day
Verify PF2 M&C manager
0%Tue 6/26/01Tue 6/26/011 day
Verify observing catalogs/tables
100%Tue 1/2/01Tue 1/2/011 day
Verify continuum tracking observing script
100%Tue 1/23/01Tue 1/23/011 day
Implement and verify continuum cross-scans observing script
100%Wed 1/24/01Wed 1/24/011 day
Implement and verify PF and Greg. focus tracking script
100%Thu 1/18/01Thu 1/18/011 day
Implement acceptance of pointing results from Aips++
100%Thu 1/25/01Fri 1/26/013 days
Implement and verify continuum OTF mapping observing script
100%Fri 2/9/01Fri 2/9/011 day
Implement and verify continuum beam-switching observing script
0%Wed 2/21/01Wed 2/21/011 day
Implement and verify continuum polarization-switching observing script
0%Tue 2/20/01Tue 2/20/011 day
Implement and verify continuum on-off observing script
0%Fri 6/29/01Fri 6/29/011 day
Implement and verify continuum 5-point observing script
0%Mon 7/2/01Mon 7/2/011 day
Implement and verify continuum grid mapping observing script
0%Fri 7/13/01Sat 7/14/011 day
Verify line tracking observing script
100%Mon 4/30/01Mon 4/30/011 day
Implement and verify line position-switching observing script
0%Thu 2/22/01Thu 2/22/011 day
Implement and verify line frequency-switching observing script
0%Mon 4/2/01Mon 4/2/011 day
Implement and verify line beam-switching observing script
0%Wed 7/18/01Wed 7/18/011 day
Implement and verify line polarization-switching observing script
0%Wed 7/18/01Thu 7/19/011 day
Implement and verify line cross-scan observing script
0%Thu 7/19/01Thu 7/19/011 day
Implement and verify line 5-point observing script
0%Thu 7/19/01Thu 7/19/011 day
Implement and verify line OTF mapping observing script
0%Thu 9/20/01Thu 9/20/011 day
Implement and verify line Grid mapping observing script
0%Mon 9/24/01Mon 9/24/011 day
Verify Doppler tracking on a test CW source
0%Tue 5/29/01Thu 5/31/016 days
Implement and verify OTF holographic script
0%Fri 2/23/01Sat 2/24/013 days
Implement and verify GO I.F./ L.O. routing
0%Wed 5/2/01Sat 5/5/019 days
Pulsar observing techniques
0%Tue 6/5/01Fri 6/8/019 days
VLBI observing techniques
0%Wed 4/4/01Sat 4/7/019 days
Verify Aips++ DCR filler
100%Wed 1/3/01Thu 1/4/013 days
Verify Holography Filler
0%Tue 4/3/01Wed 4/4/013 days
Verify Aips++ Spectrometer fillers
0%Tue 4/10/01Thu 4/12/016 days
Verify Aips++ Spectral Processor filler
88%Sat 5/5/01Mon 5/7/016 days
Examine I.F. bandpass for birdies
0%Wed 6/13/01Fri 6/15/016 days
Monitor and Control
39%Wed 1/3/01Mon 4/29/02135.25 days
DCR tests
100%Wed 1/10/01Wed 1/10/010.5 days
Test Switch Sig Sel
0%Tue 1/23/01Tue 1/23/011 day
Implement Spectrometer low-speed 3-level sampler modes
50%Wed 1/24/01Wed 2/7/0110 days
Verify M&C manager robustness - Spectrometer
13%Wed 3/7/01Fri 3/9/012 days
Implement Spectrometer high-speed sampler modes
50%Thu 2/15/01Fri 2/23/015 days
Implement Spectrometer 9-level modes
50%Fri 2/23/01Fri 3/2/015 days
Implement Spectrometer pulsar mode
100%Fri 7/6/01Fri 7/20/0110 days
Implement LO1 Counter
0%Fri 2/9/01Fri 2/16/015 days
Verify M&C manager robustness - LO1 Counter
0%Thu 3/29/01Fri 3/30/011 day
Verify M&C manager robustness - Holography
0%Thu 2/1/01Thu 2/1/011 day
Implement 40-52 GHz M&C manager
0%Fri 2/2/01Fri 2/9/015 days
Verify 40-52 GHz M&C manager
0%Mon 4/9/01Tue 4/10/012 days
Implement spectral Line - SP
50%Thu 3/8/01Wed 3/28/015 days
Implement pulsar - SP
0%Tue 6/19/01Tue 6/26/015 days
Implement PF2 M&C manager
0%Mon 6/4/01Mon 6/11/015 days
Verify PF2 M&C manager
0%Tue 6/26/01Tue 6/26/011 day
Verify ephemeredes calculations
63%Wed 1/3/01Mon 1/8/014 days
Verify refraction calculations
63%Tue 1/9/01Fri 1/19/014 days
Verify proper use of pointing coefficients
100%Mon 1/15/01Tue 1/16/012 days
Verify continuum tracking observing script
100%Tue 1/23/01Tue 1/23/010.5 days
Implement and verify continuum cross-scans observing script
100%Wed 1/24/01Wed 1/24/010.5 days
Implement and verify PF and Greg. focus tracking script
100%Thu 1/18/01Thu 1/18/010.5 days
Implement and verify continuum OTF mapping observing script
100%Fri 2/9/01Fri 2/9/010.5 days
Implement and verify continuum beam-switching observing script
0%Wed 2/21/01Wed 2/21/010.25 days
Implement and verify continuum polarization-switching observing script
0%Tue 2/20/01Tue 2/20/010.25 days
Implement and verify continuum on-off observing script
0%Fri 6/29/01Mon 7/2/010.25 days
Implement and verify continuum 5-point observing script
0%Mon 7/2/01Mon 7/2/010.25 days
Implement and verify continuum grid mapping observing script
0%Fri 7/13/01Mon 7/16/010.25 days
Verify line tracking observing script
100%Mon 4/30/01Mon 4/30/010.5 days
Implement and verify line beam-switching observing script
0%Wed 7/18/01Wed 7/18/010.25 days
Implement and verify line polarization-switching observing script
0%Wed 7/18/01Thu 7/19/010.25 days
Implement and verify line cross-scan observing script
0%Thu 7/19/01Fri 7/20/010.25 days
Implement and verify line 5-point observing script
0%Thu 7/19/01Thu 7/19/010.25 days
Implement and verify line OTF mapping observing script
0%Thu 9/20/01Thu 9/20/010.5 days
Implement and verify line Grid mapping observing script
0%Mon 9/24/01Mon 9/24/010.25 days
Implement Doppler tracking algorithm
0%Tue 5/22/01Wed 5/23/012 days
Implement and verify OTF holographic script
0%Fri 2/23/01Fri 2/23/010.5 days
Pulsar observing techniques
0%Tue 6/5/01Thu 6/7/012 days
VLBI observing techniques
0%Wed 4/4/01Thu 4/5/012 days
Specify VLBI software interfaces
100%Fri 3/16/01Thu 3/22/015 days
Upgrade VLBA software to current version
75%Tue 4/24/01Thu 5/3/015 days
Design VLBI software communication
75%Fri 5/18/01Fri 5/25/015 days
Code and test VLBI software
65%Fri 5/25/01Mon 6/4/015 days
Specify new S2 communication software
0%Tue 4/16/02Mon 4/22/025 days
Implement S2 system with GBT
0%Tue 4/23/02Mon 4/29/025 days
Upgrade VLBA formatter for 2-recorders
0%Thu 4/18/02Wed 4/24/025 days
Complete optical telescope software
0%Thu 1/25/01Wed 1/31/015 days
Implement and verify line position-switching observing script
0%Thu 2/22/01Thu 2/22/010.5 days
Implement and verify line frequency-switching observing script
0%Mon 4/2/01Mon 4/2/010.25 days
Test LO1 manager
100%Fri 1/12/01Fri 1/12/011 day
Test I.F. manager
100%Tue 1/16/01Wed 1/17/011 day
Verify Doppler tracking on a test CW source
0%Wed 5/30/01Wed 5/30/011 day
Measure Spectrometer bandpass on CW signal - low speed
50%Fri 4/20/01Tue 5/1/012 days
Measure Spectrometer bandpass on CW signal - high speed
56%Mon 7/2/01Tue 7/10/011 day
Measure Spectrometer bandpass on CW signal - 9-level
6%Tue 7/3/01Fri 7/13/011 day
Prepare for and move actuators according to photogrammetry results
0%Tue 9/18/01Wed 9/19/012 days
Engineering
32%Wed 1/3/01Mon 4/29/02180 days
Implement Spectrometer low-speed 3-level sampler modes
50%Wed 1/24/01Wed 2/7/0120 days
Implement Spectrometer high-speed sampler modes
50%Thu 2/15/01Fri 2/23/0110 days
Implement Spectrometer 9-level modes
50%Fri 2/23/01Fri 3/2/0110 days
Implement Spectrometer pulsar mode
100%Fri 7/6/01Fri 7/13/0110 days
Implement LO1 Counter
0%Fri 2/9/01Fri 2/16/015 days
Measure Holography phase stability on CW signal
0%Thu 2/8/01Thu 2/8/010.5 days
Verify Doppler tracking on a test CW source
0%Wed 5/30/01Wed 5/30/011 day
Determine telescope acceleration
100%Thu 2/1/01Thu 2/1/011 day
Determine settling time
0%Mon 2/5/01Mon 2/5/011 day
Determine 800 MHz axial focus curve (f,pol)
0%Tue 7/3/01Tue 7/3/011 day
Measure 800 MHz collimation
0%Mon 12/17/01Mon 12/17/011 day
Observe 800 MHz gain calibrators(f,pol)
0%Wed 12/19/01Wed 12/19/011 day
Measure 800 MHz inner beam maps(f,pol)
100%Thu 12/27/01Fri 12/28/011 day
Measure 800 MHz bandpass(f.pol) and baselines(f,pol)
0%Mon 12/24/01Mon 12/24/011 day
Measure 800 MHz beam squint(f)
100%Tue 1/1/02Wed 1/2/021 day
Determine 800 MHz polarization hybrid settings(f)
0%Tue 12/25/01Tue 12/25/011 day
Determine 1-2 GHz axial focus curve (f,pol)
0%Mon 12/31/01Mon 12/31/011 day
Measure 1-2 GHz MHz collimation
0%Thu 12/13/01Fri 12/14/011 day
Observe 1-2 GHz gain calibrators(f,pol)
0%Thu 1/3/02Fri 1/4/021 day
Measure 1-2 GHz inner beam maps(f,pol)
0%Mon 1/7/02Mon 1/7/021 day
Measure 1-2 GHz bandpass(f.pol) and baselines(f,pol)
0%Tue 1/8/02Tue 1/8/021 day
Measure 1-2 GHz beam squint(f)
0%Thu 1/10/02Thu 1/10/021 day
Determine 1-2 GHz polarization hybrid settings(f)
0%Fri 1/11/02Fri 1/11/021 day
Determine 12-18 GHz axial focus curve (f,pol)
0%Thu 1/17/02Thu 1/17/021 day
Measure 12-18 GHz MHz collimation
0%Fri 1/18/02Fri 1/18/021 day
Determine 12-18 GHz beam-switching blanking
0%Fri 12/7/01Mon 12/10/011 day
Observe 12-18 GHz gain calibrators(f,pol)
0%Mon 1/21/02Mon 1/21/021 day
Measure 12-18 GHz inner beam maps(f,pol)
0%Mon 1/21/02Mon 1/21/021 day
Measure 12-18 GHz bandpass(f.pol) and baselines(f,pol)
0%Tue 1/22/02Tue 1/22/021 day
Measure 12-18 GHz beam squint(f)
0%Wed 1/23/02Wed 1/23/021 day
Determine 40-52 GHz axial focus curve (f,pol)
0%Fri 1/25/02Fri 1/25/021 day
Measure 40-52 GHz MHz collimation
0%Mon 1/28/02Mon 1/28/021 day
Determine 40-52 GHz beam-switching/tertiary blanking
0%Mon 1/28/02Wed 1/30/023 days
Observe 40-52 GHz gain calibrators(f,pol)
0%Thu 1/31/02Thu 1/31/021 day
Measure 40-52 GHz inner beam maps(f,pol)
0%Mon 2/4/02Mon 2/4/021 day
Measure 40-52 GHz bandpass(f.pol) and baselines(f,pol)
0%Tue 2/5/02Tue 2/5/021 day
Measure 40-52 GHz beam squint(f)
0%Thu 2/7/02Thu 2/7/021 day
Determine 300 MHz axial focus curve (f,pol)
0%Wed 2/20/02Wed 2/20/020.5 days
Measure 300 MHz collimation
0%Thu 2/21/02Thu 2/21/020.5 days
Observe 300 MHz gain calibrators(f,pol)
0%Fri 2/22/02Fri 2/22/020.5 days
Measure 300 MHz inner beam maps(f,pol)
0%Mon 2/25/02Mon 2/25/020.5 days
Measure 300 MHz bandpass(f.pol) and baselines(f,pol)
0%Mon 2/25/02Mon 2/25/020.5 days
Measure 300 MHz beam squint(f)
0%Tue 2/26/02Tue 2/26/020.5 days
Determine 300 MHz polarization hybrid settings(f)
0%Wed 2/27/02Wed 2/27/020.5 days
Determine 2-3 GHz axial focus curve (f,pol)
0%Thu 2/28/02Thu 2/28/020.5 days
Measure 2-3 GHz MHz collimation
0%Fri 3/1/02Fri 3/1/020.5 days
Observe 2-3 GHz gain calibrators(f,pol)
0%Mon 3/11/02Mon 3/11/020.5 days
Measure 2-3 GHz inner beam maps(f,pol)
40%Mon 3/11/02Mon 3/11/020.5 days
Measure 2-3 GHz bandpass(f.pol) and baselines(f,pol)
0%Mon 3/4/02Mon 3/4/020.5 days
Measure 2-3 GHz beam squint(f)
100%Wed 3/13/02Wed 3/13/020.5 days
Determine 2-3 GHz polarization hybrid settings(f)
0%Mon 3/4/02Mon 3/4/020.5 days
Determine 4-6 GHz axial focus curve (f,pol)
0%Tue 3/5/02Tue 3/5/020.5 days
Measure 4-6 GHz MHz collimation
0%Wed 3/6/02Wed 3/6/020.5 days
Observe 4-6 GHz gain calibrators(f,pol)
0%Thu 3/7/02Thu 3/7/020.5 days
Measure 4-6 GHz inner beam maps(f,pol)
0%Fri 3/8/02Fri 3/8/020.5 days
Measure 4-6 GHz bandpass(f.pol) and baselines(f,pol)
0%Tue 3/12/02Tue 3/12/020.5 days
Measure 4-6 GHz beam squint(f)
0%Thu 3/14/02Thu 3/14/020.5 days
Determine 4-6 GHz polarization hybrid settings(f)
0%Mon 3/18/02Mon 3/18/020.5 days
Determine 8-10 GHz axial focus curve (f,pol)
0%Wed 3/20/02Wed 3/20/020.5 days
Measure 8-10 GHz MHz collimation
0%Thu 3/21/02Thu 3/21/020.5 days
Observe 8-10 GHz gain calibrators(f,pol)
0%Fri 3/22/02Fri 3/22/020.5 days
Measure 8-10 GHz inner beam maps(f,pol)
0%Mon 3/25/02Mon 3/25/020.5 days
Measure 8-10 GHz bandpass(f.pol) and baselines(f,pol)
0%Mon 3/25/02Mon 3/25/020.5 days
Measure 8-10 GHz beam squint(f)
0%Tue 3/26/02Tue 3/26/020.5 days
Determine 18-26 GHz axial focus curve (f,pol)
0%Thu 3/28/02Thu 3/28/021 day
Measure 18-26 GHz MHz collimation
0%Fri 3/29/02Fri 3/29/021 day
Determine 18-26 GHz beam-switching blanking
0%Mon 4/1/02Mon 4/1/021 day
Observe 18-26 GHz gain calibrators(f,pol)
0%Tue 4/2/02Tue 4/2/021 day
Measure 18-26 GHz inner beam maps(f,pol)
0%Thu 4/4/02Thu 4/4/021 day
Measure 18-26 GHz bandpass(f.pol) and baselines(f,pol)
0%Fri 4/5/02Fri 4/5/021 day
Measure 18-26 GHz beam squint(f)
0%Mon 4/8/02Mon 4/8/021 day
Determine PF2 axial focus curve (f,pol)
0%Mon 4/1/02Mon 4/1/020.5 days
Measure PF2 MHz collimation
0%Mon 4/8/02Mon 4/8/020.5 days
Observe PF2 gain calibrators(f,pol)
0%Thu 4/11/02Thu 4/11/020.5 days
Measure PF2 inner beam maps(f,pol)
0%Fri 4/12/02Fri 4/12/020.5 days
Measure PF2 bandpass(f.pol) and baselines(f,pol)
0%Mon 4/15/02Mon 4/15/020.5 days
Measure PF2 beam squint(f)
0%Mon 4/15/02Mon 4/15/020.5 days
Determine PF2 polarization hybrid settings(f)
0%Tue 4/16/02Tue 4/16/020.5 days
Complete PF2 hardware
0%Fri 6/1/01Fri 6/1/010 days
Specify VLBI software interfaces
100%Fri 3/16/01Thu 3/22/015 days
Upgrade VLBA software to current version
75%Tue 4/24/01Thu 5/3/015 days
Design VLBI software communication
75%Fri 5/18/01Fri 5/25/015 days
Code and test VLBI software
65%Fri 5/25/01Mon 6/4/015 days
Specify new S2 communication software
0%Tue 4/16/02Mon 4/22/025 days
Implement S2 system with GBT
0%Tue 4/23/02Mon 4/29/025 days
Upgrade VLBA formatter for 2-recorders
0%Thu 4/18/02Wed 4/24/025 days
Complete optical telescope hardware
0%Wed 1/3/01Tue 1/9/015 days
Determine 800 MHz polarization-switching blanking
0%Thu 10/25/01Fri 10/26/011 day
Determine 1-2 GHz polarization-switching blanking
0%Mon 12/31/01Tue 1/1/021 day
Determine 2-3 GHz polarization-switching blanking
0%Wed 1/30/02Wed 1/30/021 day
Determine 4-6 GHz polarization-switching blanking
0%Tue 2/12/02Tue 2/12/021 day
Determine PF2 polarization-switching blanking
0%Wed 2/13/02Wed 2/13/021 day
Determine 300 MHz polarization-switching blanking
0%Tue 1/29/02Tue 1/29/021 day
Check LO1 frequency
100%Thu 1/11/01Thu 1/11/011 day
Test I.F. hardware
100%Fri 1/12/01Wed 1/17/013 days
Measure clock & switching-signal delays
80%Mon 1/15/01Mon 1/15/011 day
Install spoilers
0%Thu 3/8/01Thu 3/8/011 day
Measure Spectrometer bandpass on CW signal - low speed
50%Fri 4/20/01Tue 5/1/012 days
Measure Spectrometer bandpass on CW signal - high speed
56%Mon 7/2/01Tue 7/10/011 day
Measure Spectrometer bandpass on CW signal - 9-level
6%Tue 7/3/01Fri 7/13/011 day
Prepare for and move actuators according to photogrammetry results
0%Tue 9/18/01Thu 9/20/015 days
Servo - Prime Focus
0%Thu 7/5/01Thu 7/5/011 day
Servo - actuator/turret low freq.
100%Mon 7/23/01Thu 7/26/012.5 days
Servo - actuator/turret High Freq.
0%Tue 8/7/01Thu 8/9/013 days
Aips++
15%Tue 1/2/01Mon 9/24/01107 days
Implement baseline fitting (polynomial, sinusoid)
100%Tue 1/2/01Tue 1/2/011 day
Implement Gaussian fitting (single, multi)
100%Tue 1/2/01Tue 1/2/011 day
Implement template fitting
80%Tue 1/2/01Tue 1/2/011 day
Implement observations data base
50%Wed 1/3/01Wed 1/3/011 day
Implement scripting tools
50%Wed 1/3/01Wed 1/3/011 day
Verify Aips++ DCR filler
100%Thu 1/4/01Thu 1/4/011 day
Implement multi-purpose continuum plotting tools
0%Thu 1/4/01Wed 1/10/015 days
Implement 1-d continuum OTF regridding
0%Thu 1/4/01Fri 1/5/012 days
Implement cross-scan pointing data reduction
100%Tue 1/9/01Wed 1/10/012 days
Implement 1-d focus-curve fitting
0%Fri 1/5/01Mon 1/8/012 days
Implement 2-d focus curve fitting
0%Mon 1/8/01Fri 1/12/015 days
Implement all-sky pointing data reduction
80%Thu 1/11/01Wed 1/17/015 days
Implement real-time data display and quick reduction
0%Thu 1/11/01Mon 1/15/013 days
Implement Tcal and Tsys data reduction
0%Mon 1/15/01Mon 1/15/011 day
Implement atmospheric model fitting
0%Tue 1/16/01Tue 1/16/011 day
Implement 2-d continuum regridding
0%Tue 1/16/01Wed 1/17/012 days
Implement continuum OTF mapping data reduction
0%Thu 1/18/01Fri 1/19/012 days
Implement continuum polarization data reduction
0%Thu 1/18/01Fri 1/19/012 days
Implement beam-switching data reduction
0%Thu 1/18/01Fri 1/19/012 days
Implement continuum grid mapping data reduction
0%Thu 2/22/01Fri 2/23/012 days
Implement 5-point continuum pointing data reduction
0%Wed 7/18/01Thu 7/19/012 days
Implement On-Off data reduction
0%Wed 7/18/01Thu 7/19/012 days
Verify Holography Filler
0%Tue 4/3/01Tue 4/3/011 day
Implement Amp/phase, Re/I'm, Illum/Offset plotting tools
0%Tue 1/23/01Thu 1/25/013 days
Implement real-time data display
0%Tue 1/23/01Wed 1/24/012 days
Implement 2-d Amp/phase holographic regridding
0%Tue 1/23/01Wed 1/24/012 days
Implement Step 1 instrumental corrections
0%Thu 1/25/01Mon 1/29/013 days
Implement 2-d IFFT routines
0%Thu 1/25/01Thu 1/25/011 day
Implement Step 2 instrumental corrections
0%Fri 1/26/01Tue 1/30/013 days
Implement phase-fitting routine
0%Thu 2/1/01Tue 2/6/014 days
Implement actuator offset routine
0%Thu 2/1/01Wed 2/7/015 days
Verify Aips++ Spectrometer fillers
0%Tue 4/10/01Thu 4/12/012 days
Verify Aips++ Spectral Processor filler
15%Mon 5/7/01Tue 5/8/012 days
Implement multi-purpose spectral-line plotting tools
0%Fri 2/2/01Fri 2/2/011 day
Implement real-time data display
0%Thu 2/22/01Fri 2/23/012 days
Implement 1-d spectral-line regridding
0%Wed 1/17/01Wed 1/17/011 day
Implement Position-switching data reduction
0%Mon 1/22/01Mon 1/22/011 day
Implement Frequency-switching data reduction
0%Mon 1/22/01Mon 1/22/011 day
Implement Beam and Polarization switching data reduction
0%Mon 1/22/01Mon 1/22/011 day
Implement Doppler-tracking regridding
0%Thu 2/22/01Fri 2/23/012 days
Implement 5-point spectral-line pointing data reduction
0%Wed 7/18/01Wed 7/18/011 day
Implement 3-d spectral-line regridding
0%Thu 7/19/01Mon 7/23/013 days
Implement spectral-line grid mapping data reduction
0%Fri 7/20/01Thu 7/26/015 days
Implement spectral-line OTF mapping data reduction
0%Fri 7/20/01Thu 7/26/015 days
Implement polarization data reduction
0%Tue 9/18/01Mon 9/24/015 days
Implement acceptance of pointing results from Aips++
100%Fri 1/26/01Thu 2/1/015 days
GBT Observe
29%Tue 1/2/01Mon 9/24/0141 days
Verify observing catalogs/tables
100%Tue 1/2/01Tue 1/2/010.5 days
Verify ephemeredes calculations
63%Wed 1/3/01Mon 1/8/012 days
Verify refraction calculations
63%Tue 1/9/01Fri 1/19/012 days
Verify proper use of pointing coefficients
100%Mon 1/15/01Tue 1/16/011 day
Verify continuum tracking observing script
100%Tue 1/23/01Tue 1/23/010.5 days
Implement and verify continuum cross-scans observing script
100%Wed 1/24/01Thu 1/25/011 day
Implement and verify PF and Greg. focus tracking script
25%Thu 1/18/01Tue 2/13/011 day
Implement and verify continuum OTF mapping observing script
74%Fri 2/9/01Fri 2/16/011 day
Implement and verify continuum beam-switching observing script
0%Wed 2/21/01Wed 2/21/010.5 days
Implement and verify continuum polarization-switching observing script
0%Tue 2/20/01Tue 2/20/010.5 days
Implement and verify continuum on-off observing script
0%Fri 6/29/01Mon 7/2/010.25 days
Implement and verify continuum 5-point observing script
0%Mon 7/2/01Mon 7/2/010.25 days
Implement and verify continuum grid mapping observing script
0%Fri 7/13/01Mon 7/16/010.5 days
Verify line tracking observing script
100%Mon 4/30/01Mon 4/30/010.5 days
Implement and verify line beam-switching observing script
0%Wed 7/18/01Wed 7/18/010.25 days
Implement and verify line polarization-switching observing script
0%Wed 7/18/01Thu 7/19/010.25 days
Implement and verify line cross-scan observing script
0%Thu 7/19/01Fri 7/20/010.25 days
Implement and verify line 5-point observing script
0%Thu 7/19/01Thu 7/19/010.25 days
Implement and verify line OTF mapping observing script
0%Thu 9/20/01Fri 9/21/011 day
Implement and verify line Grid mapping observing script
0%Mon 9/24/01Mon 9/24/010.25 days
Implement Doppler tracking algorithm
0%Tue 5/22/01Wed 5/23/011 day
Implement and verify OTF holographic script
0%Fri 2/23/01Mon 2/26/011 day
Implement and verify GO I.F./ L.O. routing
0%Wed 5/2/01Wed 5/16/015 days
Pulsar observing techniques
0%Tue 6/5/01Tue 6/19/015 days
VLBI observing techniques
0%Wed 4/4/01Tue 4/17/015 days
Implement acceptance of pointing results from Aips++
100%Fri 1/26/01Thu 2/8/015 days
Determine cross scans optimum parameters(f)
0%Tue 2/13/01Wed 2/14/010.5 days
Determine focus scans optimum parameters(f)
0%Wed 2/14/01Thu 2/15/010.5 days
Determine 5-point optimum parameters(f)
0%Thu 3/29/01Fri 3/30/010.5 days
Determine OTF optimum mapping parameters
0%Thu 6/21/01Thu 6/21/010.5 days
Determine beam-switching parameters
0%Tue 6/26/01Wed 6/27/010.5 days
Determine polarization switching parameters
0%Wed 6/27/01Thu 6/28/010.5 days
Determine position-switched parameters
0%Fri 6/22/01Fri 6/22/010.5 days
Determine frequency-switching parameters
0%Mon 6/25/01Mon 6/25/010.5 days
Determine grid optimum mapping parameters
0%Thu 6/28/01Fri 6/29/010.5 days
Implement and verify line position-switching observing script
0%Thu 2/22/01Thu 2/22/010.5 days
Implement and verify line frequency-switching observing script
0%Mon 4/2/01Mon 4/2/010.25 days
Wells/Schwab
9%Tue 1/2/01Thu 9/20/0145 days
Determine surface(El,temp) and actuators(El,temp)
0%Tue 1/2/01Mon 1/15/0110 days
Finite element analysis of Greg. Xt(El,temp), Y(El,temp)
0%Thu 2/15/01Fri 3/16/0120 days
Determine actuator motions from photogrammetry map
80%Thu 1/25/01Wed 1/31/015 days
Prepare for and move actuators according to photogrammetry results
0%Tue 9/18/01Thu 9/20/013 days
Synthesize focus determinations from all methods
0%Mon 8/6/01Wed 8/8/013 days
Verification of high-freq. Greg. focus coefficients
0%Tue 8/14/01Fri 8/17/014 days
Metrology
0%Thu 2/15/01Fri 8/3/0140 days
Metrology determination of Greg. Xt(El,temp), Y(El,temp)
0%Thu 2/15/01Fri 3/16/0120 days
Metrology determination of pointing coefficients
0%Mon 7/9/01Fri 8/3/0120 days
CLEO Programming
26%Fri 2/2/01Fri 8/10/0115 days
Implement Spectrometer pulsar mode
50%Fri 7/6/01Fri 8/10/015 days
Verify M&C manager robustness - LO1 Counter
0%Thu 3/29/01Thu 4/5/011 day
Code and test VLBI software
65%Fri 5/25/01Mon 6/4/011 day
Implement 40-52 GHz M&C manager
0%Fri 2/2/01Mon 2/26/013 days
Implement PF2 M&C manager
0%Mon 6/4/01Mon 6/25/013 days
Verify M&C manager robustness - Spectrometer
40%Fri 3/2/01Thu 3/15/012 days
High Frequency Weather
0%Sun 9/16/01Sun 5/5/02249.5 days
Measure high freq. Greg focus track
0%Fri 10/26/01Mon 10/29/019 days
Perform Greg high freq. all-sky map
0%Fri 11/16/01Mon 11/19/019 days
Verify Greg high freq. all-sky coefficients
0%Thu 11/22/01Fri 11/23/013 days
Make Greg. high-resolution map near rigging angle
0%Fri 9/21/01Mon 10/1/0130 days
Make Greg. Low-resolution maps at various El
0%Mon 10/1/01Thu 10/11/0130 days
Measure Greg 12 GHz Holog efficiency pre- measurements
0%Thu 10/11/01Fri 10/12/013 days
Measure Greg 12-GHz Holog efficiency improvement
0%Mon 10/22/01Tue 10/23/013 days
Measure 12-18 GHz efficiencies
0%Mon 10/29/01Tue 10/30/013 days
Measure 18-26 GHz efficiencies
0%Fri 11/2/01Sat 11/3/013 days
Measure 40-52 GHz efficiencies
0%Mon 11/19/01Thu 11/22/019 days
Measure scattering pattern - 50 GHz
0%Mon 11/26/01Tue 11/27/013 days
Measure scattering pattern - 26 GHz
0%Sat 11/24/01Sun 11/25/013 days
Measure scattering pattern - 12 GHz
0%Fri 11/23/01Sat 11/24/013 days
Determine 18-26 GHz axial focus curve (f,pol)
0%Thu 3/28/02Fri 3/29/023 days
Measure 18-26 GHz MHz collimation
0%Fri 3/29/02Sat 3/30/023 days
Observe 18-26 GHz gain calibrators(f,pol)
0%Tue 4/2/02Thu 4/4/026 days
Measure 18-26 GHz inner beam maps(f,pol)
0%Thu 4/4/02Fri 4/5/023 days
Measure 18-26 GHz bandpass(f.pol) and baselines(f,pol)
0%Fri 4/5/02Sat 4/6/023 days
Measure 18-26 GHz beam squint(f)
0%Sat 4/6/02Sun 4/7/023 days
Determine 12-18 GHz axial focus curve (f,pol)
0%Thu 1/17/02Fri 1/18/023 days
Measure 12-18 GHz MHz collimation
0%Fri 1/18/02Sat 1/19/023 days
Observe 12-18 GHz gain calibrators(f,pol)
0%Sat 1/19/02Sun 1/20/023 days
Measure 12-18 GHz inner beam maps(f,pol)
0%Sun 1/20/02Mon 1/21/023 days
Measure 12-18 GHz bandpass(f.pol) and baselines(f,pol)
0%Tue 1/22/02Wed 1/23/023 days
Measure 12-18 GHz beam squint(f)
0%Wed 1/23/02Thu 1/24/023 days
Determine 40-52 GHz axial focus curve (f,pol)
0%Fri 1/25/02Sun 1/27/026 days
Measure 40-52 GHz MHz collimation
0%Sun 1/27/02Mon 1/28/023 days
Observe 40-52 GHz gain calibrators(f,pol)
0%Thu 1/31/02Sun 2/3/029 days
Measure 40-52 GHz inner beam maps(f,pol)
0%Sun 2/3/02Tue 2/5/026 days
Measure 40-52 GHz bandpass(f.pol) and baselines(f,pol)
0%Tue 2/5/02Thu 2/7/026 days
Measure 40-52 GHz beam squint(f)
0%Thu 2/7/02Fri 2/8/023 days
Measure PF 12 GHz FE efficiency pre-measurements
0%Fri 10/12/01Sat 10/13/013 days
Measure 12 GHz photogrammetry efficiency pre- measurements
0%Sun 9/16/01Mon 9/17/013 days
Measure 12-GHz photogrammetry efficiency improvement
0%Thu 9/20/01Fri 9/21/013 days
Measure PF 12-GHz FE efficiency improvement
0%Mon 10/15/01Tue 10/16/013 days
Make PF High-resolution map near rigging angle
0%Thu 4/25/02Tue 4/30/0215 days
Make PF Low-resolution maps at various El
0%Tue 4/30/02Sun 5/5/0215 days
Measure Hol Greg. pointing collimation
0%Mon 9/17/01Mon 9/17/011.5 days
Determine Hol. Greg. axial focus curve
0%Mon 9/17/01Tue 9/18/011.5 days
Measure Hol. Greg. phase stability on calibrator
0%Tue 9/18/01Tue 9/18/012 days
Measure Hol PF pointing collimation
0%Mon 4/22/02Mon 4/22/021 day
Determine Hol PF axial focus curve
0%Wed 4/24/02Wed 4/24/021.5 days
Measure Hol PF phase stability on calibrator
0%Wed 4/24/02Thu 4/25/022 days
Measure 12 GHz outer sidelobes
0%Sat 12/8/01Thu 12/13/0115 days