GBT VLBA PROJECT SETUP

Observer's Name: Carilli et al
Project ID: BC132A [ABC132_01] BC132B [ABC132_02]
Description Highest redshift FIR luminous QSOs
Receiver: Rcvr1_2
Receiver Tuning Frequency: 1420
Start Date/Time: Wed Apr 16, 2003 02:00 [EDT: Tues Apr 15, 10:00pm] Sat Apr 19, 2003 01:00 [EDT: Fri Apr 18, 09:00pm]
End Date/Time: Wed Apr 16, 2003 09:00 [EDT: 05:00am] Sat Apr 19, 2003 08:00 [EDT: 04:00am]
Number of tapes: 2 2
Tapes change times: 07:11UT 06:12 [EDT: 02:12]
Receiver pol:
gain, phase, atten:
filter:
circular
x=+3, y=-6, phase=83.5
1.3-1.45
LO1 center F0:
phase cal?
1300
yes : 1MHz

Signal Routing
Rcvr IFRack IF Filter Fiber Cnv.Rack Cnv.LO2 DAR channel
Rcvr1_2:XL S1 2840-3160 6 A,CM1 12750 C
Rcvr1_2:YR S3 2840-3160 8 A,CM5 12750 A