Photographic Construction Timeline
of the
Green Bank Telescope

(Photos Courtesy Ron Monk, NRAO,AUI)


1991


1991 1992 1993 1994 1995 1996 1997 1998 1999 2000

Senator Robert C. Byrd,
Dr. Walter E. Massery , Director of the National Science Foundation,
and Dr. Robert E. Hughes, President of Assoc. Universities Inc.
Groundbreaking May 1st
Cutting into the rock at the bottom of the Alidade foundation.
July
Setting forms for the first concrete pour of the Alidade footer.
August
Setting reinforcing steel in the seventh segment of the track.
August
The South wing butress wall.
September
Pouring concrete in the #6 lower wall segment.
October

1992



1991 1992 1993 1994 1995 1996 1997 1998 1999 2000

Finished Concrete Pour.
January
Pintle Bearing Form.
January
Completed East Grade Beam.
May
Bringing in the heavy equipment.
June
Track sections are laid out to be sandblasted and painted.
September

1993



1991 1992 1993 1994 1995 1996 1997 1998 1999 2000

Looking over the first level of the Alidade.
February
The Alidade
June
Lowering in the Servo Room.
July
Beams being dropped into level 4.
October
Elevation Bearings Weldment Sections.
November
Progress of Alidade
December


1994



1991 1992 1993 1994 1995 1996 1997 1998 1999 2000

Finishing off the West Tower.
February
Bringing in the first Weldment Assembly.
April
Both assemblies are now in place.
May
Temporary support structure for the Elevation Bearing.
August
Ligning up the Elevation Bearing Shaft.
September

1995



1991 1992 1993 1994 1995 1996 1997 1998 1999 2000

Lifting the second Elevation Shaft Assembly.
May
The Elevation Axle in place.
June
Gear Sector Segment set into the Fixed Stow Pin Assembly.
July
Installing the Gear Sector Segments.
August
Alidade with the Wheel Keel Plates in place.
October

1996



1991 1992 1993 1994 1995 1996 1997 1998 1999 2000

Counter weights have been added to the elevation gear.
January
Starting to assemble the box structure.
February
Elevation Wheel/Counterweight assembly.
March
Assembling the backup structure supports.
April
The Subreflector truss.
June
Pre-assembling the backup structure.
June
Backup structure.
July
A section of the Horizontal Feed Arm being lifted into place.
October
The first sections of the Horizontal Feed Ar are now in Place.
December

1997



1991 1992 1993 1994 1995 1996 1997 1998 1999 2000

Next section of the Horizontal Feed Arm.
February
Trial Assembly of the Backup Structure.
March
Center section of the Horizontal Feed Arm.
May
Completed trial assembly of the Backup Structure.
June
Starting to move the Backup Structure to the GBT.
September
More modules in place.
December

1998



1991 1992 1993 1994 1995 1996 1997 1998 1999 2000
\
Module R-7 being added.
February
Adding BUS Module L-10.
March
Adding BUS Module L-10.
April
Dropping in Module R-8.
June
All Module in place.
July
Overall View
August
Adding to the Vertical Feed Arm.
October

1999



1991 1992 1993 1994 1995 1996 1997 1998 1999 2000

Looking West
February
Trial fitting of the last two sections of the vertical feed arm.
April
Telescope is tilted to 12 degrees to accept the last sections of the feed arm.
June
Subreflector and Feed Arm being dropped into place.
July
The first Surface Panels are added.
August
More panels added.
November

2000



1991 1992 1993 1994 1995 1996 1997 1998 1999 2000

Almost Done
January
The Big Picture