Day Shift 0700-1900 Operator: Barry Sharp
o 0700-0800 Commissioning (Maddelena, 9 GHz)
o 0800-1715 Maintenance/Outfitting:
Upper elevator inspection and maintenance
Concrete pads poured for laser mounts
Azimuth truck #3 maintenance
Servo room potentiometer calibration
Fuse replaced in lower elevator
Troublshooting of IF rack in receiver room
o 1715-1900 Commissioning (Ghigo, Polarization tests)
Night Shift: 1900-0700 Operator: Greg Monk
o 1900-0000 Commissioning (Ghigo, Polarization tests)
o 0000-0700 Commissioning (Roshi, 822 MHz)
J. Lawrence 04/22/02