Day Shift: 0700-1900 Operator: Barry Sharp
o 0700-0800 Observation 2A021 (Balser, 2400 MHz)
o 0800-1630 Maintenance/Outfitting:
Track cover maintenance done.
Inspection and survey of track by grout company.
4_6 GHz receiver installed.
Installation of RFI junction box for subreflector actuator.
Walk through completed.
o 1630-1900 Commissioning (Maddalena, 5000 MHz)
Night Shift: 1900-0700 Operator: Greg Monk
o 1900-1930 Commissioning (Maddalena, 5000 MHz)
o 1930-0700 Commissioning (Maddalena, 9000 MHz)
J. Lawrence 04/22/2002