GBT Daily Summary for Fri Apr 12, 2002
Past Summaries
Current Daily Summary
GB Home Page
GB Telescope Operations Home Page
Day Shift: 0700-1900 Operator: Dave Rose
o 0700-0830 Commissioning (Maddelena, 22 GHz)
o 0830-1030 Maintenance/Outfitting:
Track work - holes drilled
Check done on HVAC
Cryo tank delivered to cryo room, level 2
Laser Metrology testing continued
o 1030-1527 Commissioning (Maddelena, 22 GHz)
o 1527-1807 Maintenance/Outfitting:
Track cover installation
o 1807-1900 Commissioning (Roshi, 800 MHz)
Night Shift: 1900-0700 Operator: Barry Sharp
o 1900-0700 Commissioning (Roshi, 800 MHz)
J. Lawrence 04/17/2002