Day Shift: 0700-1900 Operator: Barry Sharp
o 0730-1700 Maintenance/Outfitting:
Track cover modifications continued
Modified subreflector junction boxes
Track cover spring tests accomplished
Laser Metrology testing continued
o 1700-1900 Commissioning (Maddelena, 22 GHz)
Night Shift: 1900-0700 Operator: Greg Monk
o 1900-0700 Commissioning (Maddelena, 22 GHz)
J. Lawrence 04/11/02