GBT Daily Summary for Mon Apr 8, 2002
Past Summaries
Current Daily Summary
GB Home Page
GB Telescope Operations Home Page
Day Shift: 0700-1900 Operator: Greg Monk
o 0730-1730 Maintenance/Outfitting:
Azimuth track fins installed
C-band receiver prep work
Quadrant detector measurements taken
Optical fiber driver module #7 installed
Receiver room temp problem investigated
Checked out water in surface actuators
o 1730-1900 Commissioning (Balser, 22.235 GHz)
Night Shift: 1900-0700 Operator: Kevin Gum
o 1900-0700 Commissioning (Balser, 22.235 GHz)
J. Lawrence 04/09/02