GBT Daily Summary for Wed Mar 27, 2002
Past Summaries
Current Daily Summary
GB Home Page
GB Telescope Operations Home Page
Day Shift: 0700-1900 Operator: Dave Rose
o 0730-1330 Maintenance/Outfitting:
Continued track measurements
Pulled plastic wrap from track
Installed panel covers in servo room
Checked active surface work
o 1330-1830 Azimuth track tests (Weadon)
o 1830-1900 (Commissioning-active surface tests, Balser 20 GHz)
Night Shift: 1900-0700 Operator: Barry Sharp
o 1900-0700 (Commissioning-active surface tests, Balser 20 GHz)
J. Lawrence 03/28/02