GBT Daily Summary for Wed Mar 13, 2002
Past Summaries
Current Daily Summary
GB Home Page
GB Telescope Operations Home Page
Day Shift: 0700-1900 Operator: Greg Monk
o 0800-1545 Maintenance/Outfitting:
Repaired optical encoder installed
Track checked for water seepage
Reinstalled L-band RF plate
Cabled IF rack noise source to test tone router
Holography receiver checkout
o 1545-1900 Commissioning (Maddelena, Holography, 12 GHz)
Night Shift: 1900-0700 Operator: Dave Rose
o 1900-2012 Commissioning (Maddelena, Holography, 12 GHz)
o 2012-0030 GO tests (Minter)
o 0030-0700 Commissioning (Balser, 9 GHz)
J. Lawrence 03/14/02