Day Shift: 0700-1900    Operator: Dave Rose

o  0800-1630    Maintenance/Outfitting:
                Repaired conduit to tach on az motor #6
                Portion of L-band receiver removed
                600 MHz feed installed
                Az track covers worked on
                                
o  1630-1900    Commissioning (Maddelena, 22.4 GHz)


Night Shift: 1900-0700  Operator: Barry Sharp

o  1900-0700    Commissioning (Maddelena, 22.4 GHz)
J. Lawrence 03/12/02