GBT Daily Summary for Thu Mar 7, 2002
Past Summaries
Current Daily Summary
GB Home Page
GB Telescope Operations Home Page
Day Shift: 0700-1900 Operator: Eric Knapp
o 0800-1630 Maintenance/Outfitting:
Az track grout work
Metrology software testing
Installed holography receiver interface
Continued with panel gap measurements
o 1630-1900 Not Scheduled (Grout curing)
Night Shift: 1900-0700 Operator: Kevin Gum
o 1900-0000 Not Scheduled (Grout curing)
o 0000-0300 Science (GBT02A-039)
o 0300-0700 Science (GBT01A-017)
J. Lawrence 03/08/02