GBT Daily Summary for Thu Feb 28, 2002
Past Summaries
Current Daily Summary
GB Home Page
GB Telescope Operations Home Page
Day Shift: 0700-1900 Operator: Eric Knapp
o 0800-1600 Maintenance/Outfitting:
Checked out three surface actuators
Installed filters on PBX box
Worked on L-band receiver
Continued on track cover modifications
o 1600-1900 Commissioning (Balser, 1410 MHz)
Night Shift: 1900-0700 Operator: Kevin Gum
o 1900-2100 Commissioning (Balser, 1410 MHz)
o 2100-0030 Commissioning (Maddelena, Holography)
o 0030-0300 Science (Stairs, GBT02A-039)
o 0300-0700 Science (Stairs, GBT01A-017)
J. Lawrence 03/01/02