GBT Daily Summary for Wed Feb 20, 2002
Past Summaries
Current Daily Summary
GB Home Page
GB Telescope Operations Home Page
Day Shift: 0700-1900 Operator: Eric Knapp
o 0730-1630 Maintenance/Outfitting:
Spread gravel around GBT
Continued work on warehouse canteen
Worked on door gasket in servo room
Sealed signal distribution box at base of feedarm
Installed track cover wings
Installed louvre motors on generator housing
Took further azimuth track measurements
o 1630-1900 Commissioning (Balser, 1410 MHz)
Night Shift: 1900-0700 Operator: Kevin Gum
o 1900-2100 Commissioning (Balser, 1410 MHz)
o 2100-0700 Commissioning (Fisher, Galaxy Survey)
J. Lawrence 02/21/02