Day Shift: 0700-1900 Operator: Donna Stricklin
o 0730-1630 Maintenance/Outfitting:
Removed fire extinguisher from receiver room to modify bracket
Installed feedroom conduit
Measured for PBX filter in servo room
Installed quad detector
o 1630-1900 Commissioning (Maddelena, 11999 MHz)
Night Shift: 1900-0700 Operator: Eric Knapp
o 1900-0700 Commissioning (Maddelena, 11999 MHz)