GBT Daily Summary for Mon Feb 11, 2002

Past Summaries   Current Daily Summary  
GB Home Page   GB Telescope Operations Home Page  


Day Shift: 0700-1900    Operator: Eric Knapp
                
o  0730-1630    Maintenance/Outfitting:
                Checked out generator louvres
                Worked on servo monitor system
                Prep work for panel removal
                
o  1630-1900    Commissioning (Maddelena, 12000 MHz)


Night Shift: 1900-0700  Operator: Kevin Gum

o  1630-1945    Commissioning (Maddelena, 12000 MHz)

o  1945-0700    Commissioning (Ghigo, 14000 MHz)
J. Lawrence 02/12/02