GBT Daily Summary for Mon Jan 21, 2002
Past Summaries
Current Daily Summary
GB Home Page
GB Telescope Operations Home Page
Day Shift: 0700-1900 Operator: Kevin Gum
o 0800-1630 Maintenance/Outfitting:
Tool boxes installed in receiver room
PF feed change
Electrical work
Cabling done to support actuator computer improvements
o 1630-1900 Commissioning (Fisher, Galaxy Survey)
Night Shift: 1900-0700 Operator: Dave Rose
o 1900-2100 Commissioning (Fisher, Galaxy Survey)
o 2100-0045 Commissioning (Balser, 800 MHz)
o 0045-0700 Commissioning (Fisher, Galaxy Survey)
J. Lawrence 01/22/02