Day Shift: 0700-1900 Operator: Donna Stricklin
o 0800-1900 Maintenance/Outfitting:
Closed L-band dewar valve
Tested Holography receiver
Power checks on interface cabinet circuit boards(servo room)
Servo system software testing
Night Shift: 1900-0700 Operator: Greg Monk
o 1900-0610 Commissioning (Maddelena/Langston, 8000-10000 MHz)
o 0610-0700 Science (Stairs, GBT01A-075)