Day Shift: 0700-1900    Operator: Dave Rose
                
o  0800-1630 Maintenance/Outfitting:
                Install new servo lockout system
                Cryo pumps inspection
                Install final section of track covers

o  1630-1900    Commissioning (Langston, 1.42/22.2 GHz)


Night Shift: 1900-0700  Operator: Donna Stricklin

o  1900-2000    Commissioning (Langston, 1.42/22.2 GHz)

o  2000-0700    Commissioning (Galaxy Survey, 1420 MHz)
J. Lawrence 01/03/02