GBT Daily Summary for Mon Dec 17, 2001
Past Summaries
Current Daily Summary
GB Home Page
GB Telescope Operations Home Page
Day Shift: 0700-1900 Operator: Greg Monk
o 0800-1630 Maintenance/Outfitting:
Upper elevator checkout
Surface actuator repair
LO1 router/rack work
Work on switching signal distribution system
o 1630-1900 Commissioning (Prestage, 1420 MHz)
Night Shift: 1900-0700 Operator: Donna Stricklin
o 1900-2200 Commissioning (Prestage, 1420 MHz)
o 2200-0700 Commissioning (Fisher, Galaxy Survey, 1420 MHz)
J. Lawrence 12/18/01