GBT Daily Summary for Thu Dec 13, 2001
Past Summaries
Current Daily Summary
GB Home Page
GB Telescope Operations Home Page
Day Shift: 0700-1900 Operator: Eric Knapp
o 0800-1630 Maintenance/Outfitting:
Tested holography backend
Worked on 10 MHz signal in the receiver room
Junction box work for laser mounts
Lubricated prime focus boom
Measured stairs to alidade for extension
o 1630-1900 Not Scheduled
Night Shift: 1900-0700 Operator: Kevin Gum
o 1900-2100 Commissioning (Prestage, 1420 MHz)
o 2100-0300 Commissioning (Langston, 12178 MHz)
o 0300-0700 Commissioning (Fisher, Galaxy Survey, 1420 MHz)
J. Lawrence 12/14/01