Day Shift 0700-1900     Operator:  Eric Knapp

o  0800-1740  Maintenance/Outfitting:
                Switchgear work, on generator power
                Labeling of telephone wires
                Cryo compressor charge
                Prime Focus rack problem diagnosis

                
o  1740-1900 Not Scheduled

Night Shift: 1900-0700  Operator: Greg Monk

o  1900-2000  Photo-taking (Greg M.)

o  2000-0700 Commissioning (Maddelena 12178 MHz)