GBT Daily Summary for Mon Sep 17, 2001

Past Summaries   Current Daily Summary  
GB Home Page   GB Telescope Operations Home Page  


Day Shift 0700-1900     Operator: Dave Rose

o  0700-1600 Maintenance/Outfitting:
                Actuator sealing
                Level 4 painting
                Stud removal on dish surface
                AC chiller work on level 2
                

o  1600-1900 Commissioning (Ghigo/Langston- 1.46 GHz)

Night Shift: 1900-0700  Operator: Donna Stricklin

o  1900-0700 Commissioning- (Ghigo/Langston- 1.46 GHz)
J. Lawrence 10/16/01