GBT Daily Summary for Thu Sep 6, 2001
Past Summaries
Current Daily Summary
GB Home Page
GB Telescope Operations Home Page
Day Shift 0700-1900 Operator: Donna Stricklin
o 0700-1800 Maintenance/Outfitting:
Elevation gear checkout with COMSAT
S-Band receiver removed
Rerouted lightning detectors to warehouse
Replaced faulty Ground Fault Interrupter outlets on feedarm
Daily Walkthrough
o 1800-1900 L-Band SP test (Stairs)
Night Shift: 1900-0700 Operator: Eric Knapp
o 1900-2200 L-Band spectral processor test (Stairs)
o 2200-1115 L-band BCPM test (Stairs)
o 1115-0700 Not Scheduled
J. Lawrence 10/16/01