Day Shift 0700-1900 Operator: Greg Monk
o 0800-1630 Maintenance/outfitting:
Repaired IF Rack
Worked on receiver room HVAC system
Repaired azimuth motor #2 brakes
Daily Walkthrough
Continued IF MCB work
Installed ac power for optical pointing telescope
Servo room intercom system- installed listening post mixer
Fiber optic terminations on azimuth trucks continued
Azimuth servo tests and testing of the kohlmorgen motors
Laser metrology testing
o 1630-1900 Commissioning (Balser- 1400 and 800 MHz)
Night Shift: 1900-0700 Operator: Donna Stricklin
o 1900-0700 Commissioning (Balser- 800 MHz)