GBT Daily Summary for Mon Aug 27, 2001
Past Summaries
Current Daily Summary
GB Home Page
GB Telescope Operations Home Page
Day Shift 0700-1900 Operator: Eric Knapp
o 0800-1500 Maintenance:
Replaced feed arm lightbulbs
Daily walk through inspections.
Outfitting:
Work continued on Pubic Address/listening station cabling
Temperature controller installed in receiver room
Azimuth brake tests completed
Further fiber optic connectors installed (at vertex)
Software testing in servo room on MCBs
o 1700-1900 Commissioning (9 GHz- Maddelena)
Night Shift: 1900-0700 Operator: Bill Campbell
o 1900-0700 Commissioning (9 GHz- Maddelena)
J. Lawrence 10/16/01