GBT Daily Summary for Wed Aug 22, 2001
Past Summaries
Current Daily Summary
GB Home Page
GB Telescope Operations Home Page
Day Shift 0700-1900 Operator: Donna Stricklin
o 0800-1500 Maintenance/ Outfitting:
L--Band receiver removed
Daily walk through inspections.
Work done on lower elevator door
Work continued on Pubic Address system
Terminating of fiber continues
Servo room rack wired with AC for listening stations
Taping of actuators continues
o 1700-1900 Commissioning (9.0 GHz- Balser)
Other than minor problems with GO and some connection problems with the LO1 manager, things went smoothly.
Night Shift: 1900-0700 Operator: Dave Rose
o 1900-0700 Commissioning (9.0 GHz- Balser)
J. Lawrence 10/16/01