Day Shift 0700-1900 Operator: Dave Rose
o 0800-1500 Maintenance/ Outfitting:
Six month maintenance of alidade hoist "A".
Six month maintenance of prime focus hoist "C".
Start replacement of feed-arm elevator traveling cable sheave
assembly rollers.(need modification)
Daily walk through inspections.
Pubic Address cables pulled from level 4 to 2
Terminating fibers at feedarm
o 1700-1900 Commissioning (X band- RM)
Night Shift: 1900-0700 Operator: Bill Campbell
o 1900-0000 Commissioning (X band- RM)
o 0000-0700 Commissioning (X,S,L band- RM)