1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
Day | ET Time | Description | Friend | Observers | Bands | Backends | ||
---|---|---|---|---|---|---|---|---|
1 | Th | A | 00:00 - 07:30 | GBT02A-008 A Study of the Hydrogen Reservoir Surrounding Galaxies PI: Roberts, M. S. | Maddalena, R. | | L | S |
| | M | 07:30 - 16:30 | Maintenance | | | | |
| | T | 16:30 - 17:55 | Tests for VLBI observing - Ghigo | | | | |
| | S | 17:55 - 20:40 | Setup for GBT02A-008 | | | L | S |
| | A | 20:40 - 24:00 | GBT02A-008 A Study of the Hydrogen Reservoir Surrounding Galaxies PI: Roberts, M. S. | Maddalena, R. | | L | S |
2 | Fr | A | 00:00 - 12:35 | GBT02A-008 A Study of the Hydrogen Reservoir Surrounding Galaxies PI: Roberts, M. S. | Maddalena, R. | | L | S |
| | C | 12:35 - 14:50 | Vortex out for service | | | | |
| | T | 14:50 - 19:35 | Tests of GBT02A-008 Maddalena | | Maddalena | | |
| | S | 19:35 - 20:35 | Setup for GBT02A-052 | | | | |
| | A | 20:35 - 24:00 | GBT02A-052 Continued Multifrequency Monitoring of a Massive Pulsar System PI: Stairs, I. | Ghigo, F. D. | | 6LS | BP |
3 | Sa | A | 00:00 - 00:35 | GBT02A-052 Continued Multifrequency Monitoring of a Massive Pulsar System PI: Stairs, I. | Ghigo, F. D. | | 6LS | BP |
| | S | 00:35 - 01:35 | Setup for GBT02A-008 | | | L | S |
| | A | 01:35 - 08:35 | GBT02A-008 A Study of the Hydrogen Reservoir Surrounding Galaxies PI: Roberts, M. S. | Maddalena, R. | | L | S |
| | T | 08:35 - 13:05 | Tests of GBT01A-058/061 - Langston/Kanekar | | Langston/Kanekar | | |
| | S | 13:05 - 16:05 | Setup for BG125 | | | L | V |
| | A | 16:05 - 24:00 | BG125 A Very Deep VLBA-GBT Pilot Survey of the NDWFS PI: Garrett, M. | Ghigo, F. D. | | L | V |
4 | Su | A | 00:00 - 00:30 | BG125 A Very Deep VLBA-GBT Pilot Survey of the NDWFS PI: Garrett, M. | Ghigo, F. D. | | L | V |
| | S | 00:30 - 01:30 | Setup for GBT02A-008 | | | L | S |
| | A | 01:30 - 11:00 | GBT02A-008 A Study of the Hydrogen Reservoir Surrounding Galaxies PI: Roberts, M. S. | Maddalena, R. | | L | S |
| | C | 11:00 - 15:15 | HI Galazy Survey | | | | |
| | S | 15:15 - 16:15 | Setup for BG125 | | | L | V |
| | A | 16:15 - 24:00 | BG125 A Very Deep VLBA-GBT Pilot Survey of the NDWFS PI: Garrett, M. | Ghigo, F. D. | | L | V |
5 | Mo | A | 00:00 - 00:40 | BG125 A Very Deep VLBA-GBT Pilot Survey of the NDWFS PI: Garrett, M. | Ghigo, F. D. | | L | V |
| | C | 00:40 - 07:30 | OH Survey of IR Galaxies - Braatz | | Braatz | | |
| | M | 07:30 - 15:10 | Maintenance | | | | |
| | S | 15:10 - 16:10 | Setup for BG125 | | | L | V |
| | A | 16:10 - 24:00 | BG125 A Very Deep VLBA-GBT Pilot Survey of the NDWFS PI: Garrett, M. | Ghigo, F. D. | | L | V |
6 | Tu | A | 00:00 - 00:35 | BG125 A Very Deep VLBA-GBT Pilot Survey of the NDWFS PI: Garrett, M. | Ghigo, F. D. | | L | V |
| | C | 00:35 - 07:30 | Pulsar drift scan survaey - Stairs | | Stairs | | |
| | M | 07:30 - 16:30 | Maintenance | | | | |
| | C | 16:30 - 19:20 | Pulsar drift scan survaey - Stairs | | Stairs | | |
| | S | 19:20 - 20:20 | Setup for GBT02A-052 | | | 6LS | BP |
| | A | 20:20 - 24:00 | GBT02A-052 Continued Multifrequency Monitoring of a Massive Pulsar System PI: Stairs, I. | Ghigo, F. D. | | 6LS | BP |
7 | We | A | 00:00 - 00:15 | GBT02A-052 Continued Multifrequency Monitoring of a Massive Pulsar System PI: Stairs, I. | Ghigo, F. D. | | 6LS | BP |
| | T | 00:15 - 07:30 | Tests of baselines - Balser/Fisher | | Balser,FIsher | | |
| | M | 07:30 - 16:30 | Maintenance | | | | |
| | D | 16:30 - 24:00 | Shutdown - tract work | | | | |
8 | Th | D | 00:00 - 07:30 | Shutdown - tract work | | | | |
| | M | 07:30 - 16:30 | Maintenance | | | | |
| | T | 16:30 - 19:00 | Tests QD characterization - Balser | | Balser | | |
| | S | 19:00 - 20:00 | Setup for GBT02B-009 | | | L | P |
| | A | 20:00 - 22:00 | GBT02B-009 AU scale HI structures: a probe using scattering of pulsar signals PI: Roshi, A.D. | Balser, D. | | L | P |
| | C | 22:00 - 24:00 | HI Galaxy Survey | | | | |
9 | Fr | C | 00:00 - 04:25 | HI Galaxy Survey | | | | |
| | S | 04:25 - 05:25 | Setup for GBT02A-012 | | | L | P |
| | A | 05:25 - 07:25 | GBT02A-012 Probing HI Structure On Sub-A.U. - A.U. Scales: Hydrodynamical or MHD Turbulence PI: Minter, A. | Balser, D. | | L | P |
| | T | 07:25 - 08:55 | Tests EMS checkouts - Constantikes | | | | |
| | C | 08:55 - 11:55 | Commissioning | | | | |
| | T | 11:55 - 16:25 | Tests of QD - no anntenna | | | | |
| | T | 16:25 - 19:10 | Tests of QD - antenna motion | | | | |
| | S | 19:10 - 20:10 | Setup for GBT02A-052 | | | 6LS | BP |
| | A | 20:10 - 24:00 | GBT02A-052 Continued Multifrequency Monitoring of a Massive Pulsar System PI: Stairs, I. | Ghigo, F. D. | | 6LS | BP |
10 | Sa | A | 00:00 - 00:05 | GBT02A-052 Continued Multifrequency Monitoring of a Massive Pulsar System PI: Stairs, I. | Ghigo, F. D. | | 6LS | BP |
| | A | 00:05 - 04:05 | GBT02A-039 Searching for Radio Pulsations from the (X-ray) Pulsar J0205+6449 in SNR 3C58 PI: Camilo, F. | Ghigo, F. D. | | L | B |
| | C | 04:05 - 15:35 | Commissioning | | | | |
| | S | 15:35 - 16:35 | Setup for GBT02B-009 | | | L | P |
| | A | 16:35 - 24:00 | GBT02B-009 AU scale HI structures: a probe using scattering of pulsar signals PI: Roshi, A.D. | Balser, D. | | L | P |
11 | Su | A | 00:00 - 01:30 | GBT02B-009 AU scale HI structures: a probe using scattering of pulsar signals PI: Roshi, A.D. | Balser, D. | | L | P |
| | C | 01:30 - 14:00 | Commissioning | | | | |
| | T | 14:00 - 15:30 | Tests of GBT02A-003 | | | | |
| | S | 15:30 - 16:30 | Setup for GBT02B-009 | | | L | P |
| | A | 16:30 - 24:00 | GBT02B-009 AU scale HI structures: a probe using scattering of pulsar signals PI: Roshi, A.D. | Balser, D. | | L | P |
12 | Mo | A | 00:00 - 01:30 | GBT02B-009 AU scale HI structures: a probe using scattering of pulsar signals PI: Roshi, A.D. | Balser, D. | | L | P |
| | C | 01:30 - 07:30 | Commissioning | | | | |
| | M | 07:30 - 16:30 | Maintenance | | | | |
| | T | 16:30 - 18:45 | Tests of GBT02A-003 | | | | |
| | S | 18:45 - 19:45 | Setup for GBT02B-009 | | | L | P |
| | A | 19:45 - 21:45 | GBT02B-009 AU scale HI structures: a probe using scattering of pulsar signals PI: Roshi, A.D. | Balser, D. | | L | P |
| | C | 21:45 - 23:30 | Commissioning | | | | |
| | S | 23:30 - 24:00 | Setup for GBT02A-038 | | | L | S |
13 | Tu | S | 00:00 - 00:25 | Setup for GBT02A-038 | | | L | S |
| | A | 00:25 - 07:30 | GBT02A-038 Probing the ultra-low NH environment and outer disks of M31
and M33 PI: Thilker, D. | | | L | S |
| | M | 07:30 - 16:30 | Maintenance | | | | |
| | C | 16:30 - 18:40 | Commissioning | | | | |
| | S | 18:40 - 19:40 | Setup for GBT02B-009 | | | L | P |
| | A | 19:40 - 21:40 | GBT02B-009 AU scale HI structures: a probe using scattering of pulsar signals PI: Roshi, A.D. | Balser, D. | | L | P |
| | C | 21:40 - 23:40 | Commissioning | | | | |
| | S | 23:40 - 24:00 | Setup for GBT02A-038 | | | L | S |
14 | We | S | 00:00 - 00:35 | Setup for GBT02A-038 | | | L | S |
| | A | 00:35 - 07:30 | GBT02A-038 Probing the ultra-low NH environment and outer disks of M31
and M33 PI: Thilker, D. | | | L | S |
| | M | 07:30 - 16:30 | Maintenance | | | | |
| | S | 16:30 - 17:35 | Setup for GBT01A-040 | | | L | SP |
| | A | 17:35 - 24:00 | GBT01A-040 Corotation of the HI Halo in the Inner Galaxy PI: Lockman, F. J. | Maddalena, R. | | L | SP |
15 | Th | A | 00:00 - 04:30 | GBT01A-040 Corotation of the HI Halo in the Inner Galaxy PI: Lockman, F. J. | Maddalena, R. | | L | SP |
| | C | 04:30 - 07:30 | Commissioning | | | | |
| | M | 07:30 - 16:30 | Maintenance | | | | |
| | S | 16:30 - 17:30 | Setup for GBT02B-019 | | | L | B |
| | A | 17:30 - 24:00 | GBT02B-019 Timing of Newly Discovered Globular Cluster Pulsars PI: Stairs, I. | Ghigo, F. D. | | L | B |
16 | Fr | A | 00:00 - 01:25 | GBT02B-019 Timing of Newly Discovered Globular Cluster Pulsars PI: Stairs, I. | Ghigo, F. D. | | L | B |
| | C | 01:25 - 10:40 | Commissioning | | | | |
| | S | 10:40 - 11:40 | Setup for GBT02A-003 | | | L | S |
| | A | 11:40 - 21:40 | GBT02A-003 Do Hyperluminous IR Galaxies Produce OH Gigamasers? PI: Darling, J. | | | L | S |
| | S | 21:40 - 22:40 | Setup for GBT02B-013 | | | S | O |
| | A | 22:40 - 24:00 | GBT02B-013 Target-of-Opportunity Bistatic Radar Observations of Near-Earth Asteroids PI: Nolan, M | | | S | O |
17 | Sa | A | 00:00 - 01:40 | GBT02B-013 Target-of-Opportunity Bistatic Radar Observations of Near-Earth Asteroids PI: Nolan, M | | | S | O |
| | C | 01:40 - 19:40 | Commissioning | | | | |
| | S | 19:40 - 20:40 | Setup for GBT02B-013 | | | S | O |
| | A | 20:40 - 23:40 | GBT02B-013 Target-of-Opportunity Bistatic Radar Observations of Near-Earth Asteroids PI: Nolan, M | | | S | O |
| | C | 23:40 - 24:00 | Commissioning | | | | |
18 | Su | C | 00:00 - 12:05 | Commissioning | | | | |
| | S | 12:05 - 13:05 | Setup for GBT02B-013 | | | S | O |
| | A | 13:05 - 16:05 | GBT02B-013 Target-of-Opportunity Bistatic Radar Observations of Near-Earth Asteroids PI: Nolan, M | | | S | O |
| | C | 16:05 - 24:00 | Commissioning | | | | |
19 | Mo | C | 00:00 - 07:30 | Commissioning | | | | |
| | M | 07:30 - 10:30 | Maintenance | | | | |
| | S | 10:30 - 11:30 | Setup for GBT02B-013 | | | S | O |
| | A | 11:30 - 14:30 | GBT02B-013 Target-of-Opportunity Bistatic Radar Observations of Near-Earth Asteroids PI: Nolan, M | | | S | O |
| | M | 14:30 - 16:30 | Maintenance | | | | |
| | C | 16:30 - 24:00 | Commissioning | | | | |
20 | Tu | C | 00:00 - 07:30 | Commissioning | | | | |
| | M | 07:30 - 10:10 | Maintenance | | | | |
| | S | 10:10 - 11:10 | Setup for GBT02B-013 | | | S | O |
| | A | 11:10 - 14:10 | GBT02B-013 Target-of-Opportunity Bistatic Radar Observations of Near-Earth Asteroids PI: Nolan, M | | | S | O |
| | M | 14:10 - 16:30 | Maintenance | | | | |
| | C | 16:30 - 24:00 | Commissioning | | | | |
21 | We | C | 00:00 - 07:30 | Commissioning | | | | |
| | M | 07:30 - 16:30 | Maintenance | | | | |
| | C | 16:30 - 24:00 | Commissioning | | | | |
22 | Th | C | 00:00 - 07:30 | Commissioning | | | | |
| | M | 07:30 - 16:30 | Maintenance | | | | |
| | C | 16:30 - 24:00 | Commissioning | | | | |
23 | Fr | C | 00:00 - 16:15 | Commissioning | | | | |
| | S | 16:15 - 17:15 | Setup for BA057 | | | X | V |
| | A | 17:15 - 21:45 | BA057 Kinematics and distances of the rho Oph Protocluster PI: Andre, P. | | | X | V |
| | C | 21:45 - 24:00 | Commissioning | | | | |
24 | Sa | C | 00:00 - 16:10 | Commissioning | | | | |
| | S | 16:10 - 17:10 | Setup for BA057 | | | X | V |
| | A | 17:10 - 21:40 | BA057 Kinematics and distances of the rho Oph Protocluster PI: Andre, P. | | | X | V |
| | C | 21:40 - 24:00 | Commissioning | | | | |
25 | Su | C | 00:00 - 16:05 | Commissioning | | | | |
| | S | 16:05 - 17:05 | Setup for BA057 | | | X | V |
| | A | 17:05 - 21:35 | BA057 Kinematics and distances of the rho Oph Protocluster PI: Andre, P. | | | X | V |
| | C | 21:35 - 24:00 | Commissioning | | | | |
26 | Mo | C | 00:00 - 07:00 | Commissioning | | | | |
| | M | 07:00 - 19:00 | Maintenance | | | | |
| | C | 19:00 - 24:00 | Commissioning | | | | |
27 | Tu | C | 00:00 - 07:00 | Commissioning | | | | |
| | M | 07:00 - 19:00 | Maintenance | | | | |
| | C | 19:00 - 24:00 | Commissioning | | | | |
28 | We | C | 00:00 - 06:55 | Commissioning | | | | |
| | M | 06:55 - 18:55 | Maintenance | | | | |
| | C | 18:55 - 24:00 | Commissioning | | | | |
29 | Th | C | 00:00 - 07:05 | Commissioning | | | | |
| | M | 07:05 - 19:05 | Maintenance | | | | |
| | C | 19:05 - 24:00 | Commissioning | | | | |
30 | Fr | C | 00:00 - 15:45 | Commissioning | | | | |
| | S | 15:45 - 16:45 | Setup for BA057 | | | X | V |
| | A | 16:45 - 21:15 | BA057 Kinematics and distances of the rho Oph Protocluster PI: Andre, P. | | | X | V |
| | C | 21:15 - 24:00 | Commissioning | | | | |
31 | Sa | C | 00:00 - 15:30 | Commissioning | | | | |
| | S | 15:30 - 16:30 | Setup for GBT01A-040 | | | L | SP |
| | A | 16:30 - 24:00 | GBT01A-040 Corotation of the HI Halo in the Inner Galaxy PI: Lockman, F. J. | Maddalena, R. | | L | SP |
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31